HomeMy WebLinkAbout2016-006-A1 Quincy (Approved 2017) Gi Kf ASCAL�
AMENDMENT TO CONTRACT No. 1
Quincy Engineering
for
Professional Services
Via Avenue Bridge Replacement Project
C2015B02
Federal Project No. BHLS-5423(032), Bridge No. 49-C-0158
THIS AMENDMENT TO THE CONTRACT is made and entered into by and between
the CITY of ATASCADERO, a Municipal Corporation ("City"), and Quincy Engineering
("Consultant") All certifications and assurances as agreed to in the specifications and
contract dated April 27, 2016 are hereby incorporated into this amendment. The
following scope of work and compensation are in addition to that specified in the
aforementioned contract:
REGARDING EXHIBIT A — SCOPE OF WORK: Exhibit A Scope of Work is hereby
amended to include the items listed on the document attached to this Amendment.
REGARDING ITEM EXHIBIT B - COMPENSATION AND METHOD OF PAYMENT:
Exhibit B is hereby amended to include the Cost Proposal for Phase 2 as listed on the
document attached to this Amendment, not to exceed the total contract amendment
price of $286,033.79 as detailed in the cost breakdown provided.
All other terms of the original Contract remain in effect.
Dated: May 10, 2017
Quincy ine ing
By:
Johnit. Quincy, Presid nt
City of Atascadero
_6
By:
Rac elle Rickard, CityManager
Quincy Engineering
Professional Services
Via Avenue Bridge Replacement Project
City Project No. C20151302
Page 1 of 4
SCOPE OF WORK
Task 4.1 - Design and 65% Plans
Final bridge design will be performed in accordance with AASHTO LRFD Bridge Design
Specifications, 6th Edition, and the Caltrans Amendments dated 2014. The latest
updated versions of Caltrans bridge design manuals will also be utilized when
applicable. Seismic design will be performed in accordance with the Caltrans "Seismic
Design Criteria Version 1.7 April 2013" and the latest information available from
Caltrans Earthquake Research. The approach roadway design will be performed in
accordance with City Standards, AASHTO "A Policy on Geometric Design of Highways
and Streets" and Caltrans Standard Specifications. Cross-sections will be developed
per Consultant standards. Plan sheets will be prepared in AutoCAD 2015 with English
units and utilizing drafting standards. All plans will be signed by Consultants civil
engineer (registered in the state of California) in charge of the design, in accordance
with the Local Programs Manual. The PS&E for Via Avenue will contain 15 roadway
plan sheets and 11 bridge plan sheets.
Task 4.2 - Independent Design Check
An independent analysis of the project will be performed using the unchecked bridge
detailed plans and 65% roadway plans by an engineer that has not been intimately
involved in the design. Based upon the independent check and agreement to revisions
by the checker and designer, the plans will be revised. Independent Check comments
will be summarized and resolutions will be documented.
Task 4.3 - Construction Quantities & Estimate
The construction quantities will be prepared independently by two engineers and
checked against each other for accuracy. Quantities will be calculated in accordance
with Caltrans' practice and segregated into pay items. The estimate will show
quantities, unit costs, and a project cost summary. The estimate will be prepared in
spreadsheet format for inclusion into the City's final bid package.
Task 4.4 - Special Provisions
Consultant will use Caltrans 2015 Standard Specifications, in conjunction with Caltrans
2015 Technical Special Provisions (Chapters 8, 9, and 10). A hard copy and disc copy
(Microsoft Word) of the technical specifications will be provided for the City's review.
The City will combine these technical special provisions with its boilerplate
specifications to develop the project specifications. A construction (working days)
schedule will also be developed to determine the number of working days for the
construction contract.
Page 2 of 4
Task 4.5 -- Quality Control & Constructability Review
Consultant's senior level engineer will review the entire draft PS&E (90% PS&E)
package for uniformity, compatibility, and constructability as well as conformance with
the federal HBP program requirements.
Task 4.6 -95% PS&E and Response to Comments
After the QA/QC review has been completed and the plans, specifications, and estimate
have been updated, the 95% PS&E will be submitted to the City for their review. This
submittal will include the "red-lined" set of plans with responses to City review
comments on the 65% plans.
Task 4.7 - 100% PS&E
Upon receiving 95% review comments from the City and other agencies, each comment
will be reviewed, discussed, and addressed in writing by Consultant. All apparent
conflicts will be resolved in person or via telephone/email as necessary. Appropriate
modifications will be made to the plans, specifications, and estimate. Consultant will
furnish final Plans (pdf, and electronic AutoCAD files-excluding proprietary Civil 3D
components), Specifications (MS Word format), and Estimate (pad, and excel format)
package.
Task 4.8 - Utility Coordination
Consultant will prepare and submit "A", "B" and "C" utility coordination letters.
Task 5: Bidding and Award
Individuals that were directly involved in the design will be available during the bid
period to interpret bidder inquiries and prepare addenda if needed. When the
construction bids are opened, Consultant will be available to provide analysis and
recommendations concerning award of the contract. Consultant shall also attend pre
construction meetings if requested by City.
Task 6: (Not Applicable)
Task 7: Project Management and Meetings
Task 7.1: Project Management
Consultant will be responsible for project management to provide oversight and
coordination as necessary for prompt and successful completion of all contract services.
Consultant will prepare, submit and coordinate project invoices with City staff.
f
Task 7.2 - Kick-off Meeting/Project Team Meetings
Consultant's Project Manager, Project Engineer, and all sub consultant Project
Managers will attend a kick-off meeting. Consultant will also hold two additional in
person meetings during the course of design between the Project Manager and Project
Engineer to review City comments on the 65% Plans, and the 95% PS&E package.
Consultant will prepare agenda items, and compile project meeting minutes for
Page 3 of 4
J
distribution. A total of three (3) meetings including kick-off will be required. In addition
to in person meetings, Consultant will attend up to 36 monthly conference calls.
Page 3 of 4
i
Cost Proposa[
Phase 2 -Via Avenue Bridge Replacement Project
Date: 4/18/2017
Quincy Engineering,Inc.
Direct Labor: $83,601.50
Escalation for Multi-Year Protect(3.0%): $2,508.05
Subtotal $86,109.55
Overhead 1.639 : $141,133.54
A. Labor Subtotal $227,243.09
Subconsultant Costs:
SWCA Environmental Consultants $23,985.24
Yeh and Associates,Inc. $0.00
WRECO $11,478.75
Mcmillan Landsurveys $0.00
0 $0.00
0 $0.00
0 $0.00
0 $0.00
0 $0.00
B. Subconsultant Subtotal $35,463,gg
Other Direct Costs:
Travel (Q ac&a IRS mileage rare) 560 miles @ $0.540 $30240
Pier Dieml Hotel 2 days @ $150.00 $300.00
Delivery @ $20.00 $0.00
Vendor Reproduction I
Vellum Gla $0.00
8112 X i 1 Reproduction @ $0.00
11 X 17 Reproduction @ $0.00
Mounting Boards For Presentations @ $0.00
Newsletters Translation andprinting) $0.00
Subtotal Vendor Reproduction $0.00
Title Report @ $0.00
Miscellaneous
Prevailing Wage Differential $0.00
C. Other Direct Cost Subtotal: $602.40
Labor Subtotal A. = $227,243.09
Fixed Fee(10.0%): $22,724.31
Subconsultant Subtotal B. = $35,463.99
Fixed Fee(0.0%): $0.00
Other Direct Cost Subtotal: C. _ $602.40
Fixed Fee(0.0%): $0.00
TOTAL= $286,033.79
Page 4 of 4
Cost Proposal
Project Number.A46-200 Project Name:Phase 2-Via Avenue Bridge Replacement Project
75
O
.Q
V S J C U 7 7
N O O
cT m F -6 5 M Li U
W w ai m cn as of m Q, w o !- a c v. Q E d;
.oV .n •�
� ¢w w w w w w w w a -V
AOU O O C L E CTASKS 2
d 0. N
u�
BL MR GY AC RF GM CP VD BM PK KG MO EM PJ Direct Labor
No. F tnRislHoudyRate $76.70 576.70 $81.70 b4320 548.4D $57.40 $4520 847.70 $4420 $24.96 584.10 $7080 566.80 $3520
Phase 2
1,1 Task IA-Topographic Surveys 0 $0.00 $0 00
1.2 Task-1.2-Hydraulics 0 $0.00 $11,478.75 $11,478.75
1.3 Task 1.3-Geotechnical Studies 0 $0,00 S0 00
1.4 Task 1.4-Preliminary Engineering 0 $0.00 $0
Task 2-Environmental Review,
2 Coordination,Design and Permitting 4 1 4 $229.60 $23.985,24 $23,985.24
3 Task 3-Right of Way 0 $0.00 $0
41 Task 4.1-Design and 65%Plans 32 1 60 140 70 220 100 110 732 533.325.40 $0
4.2 Task 4.2-I ndependentCheck 100 32 132 $6,353.60 SO
Task 4.3-Construction Quantities&
4,3 Estimate 4 4 40 40 16 10 4 18 136 1 $6.503.20 $o
4,4 Task 4.4-Special Provisions 2 4 4 60 70 $4,475.80 $0
Task 4.5-Quality Control&
4.5 Constructability Review 24 24 S1.699.20 SO
Task 4.6-95%PS&E and Response to
4.6 Comments 4 20 40 20 80 20 20 10 4 218 $10,339.00 SO
4.7 Task 4.7-100%PS&E 4 10 20 10 40 10 10 5 4 113 $5,464.50 $o
Task 4.8-Utility Coordination&
4.8 Relocation 40 60 20 120 $6,816.00 So
5 Task 5-Bidding and Award 4 8 4 8 1 4 28 $1,613,20 50
6 Task 6-Construction Support Services 1 0 $0.00 $0
Task 7-Project Management and
7 Meetings 56 28 12 2 98 $6.782.00 So
0 $0.00 5o
0 SO.00 so
0 $0.00 $o
$0.00 $0
Subtotal-Hours 0 106 1741 2441 140 2041 374 32 130 140 79 32 18 2 1675 0
Other Direct Casts 0
Total Cost $0.00 $8,13020 510,735.80 510,540.60 $6,776.Oo $11,709.60 $16,904.80 $1,513.60 $5,746.00 $3,486.00 $5,063.90 $2,265.60 5658.60 $70.40 583,601.50 543 601.501 $23,985.241 $0,00 511,478.75 50.00 $0.001 535,463.99
Via Cast Prop revised 4.18.17 Phase 2.x1sa Ptaasa 2 lbs 4W,2017 r`�' Q U I N CY