HomeMy WebLinkAboutPC Resolution 2016-0025
EXHIBIT A: Conditions of Approval / Mitigation Monitoring
PLN 2016-1616 / TRP 2016-0204
Conditions of Approval
PLN 2016-1616 / TRP 2016-0204
7080 Bella Vista Road
Timing
FM; Final Map
BL: Business License
GP: Grading Permit
BP: Building Permit
FI: Final Inspection
TO: Temporary Occupancy
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
1. The approval of this application shall become final, subject to the completion
of the conditions of approval, fourteen (14) days following the Planning
Commission approval unless prior to that time, an appeal to the decision is
filed as set forth in Section 9-1.111(b) of the Zoning Ordinance.
Tree removal
PS
2. The applicant and/or subsequent owners shall defend, indemnify, and hold
harmless the City of Atascadero or its agents, officers, and employees against
any claim or action brought to challenge an approval by the City, or any of its
entities, concerning the proposed tree removal.
Ongoing PS
3. The owner or applicant shall mitigate the tree removals by replanting native
trees, making appropriate payment to the tree mitigation fund, or a
combination thereof as shown in Exhibit B. Larger box trees may be
substituted for five-gallon replacement trees per the Atascadero Native
Tree Guidelines.
Building
Permit
PS
4. Payment to the tree mitigation fund or approval of a tree replanting and
irrigation plan shall occur before trees are removed.
Building
Permit
PS
5. If tree replanting is selected, the owner or applicant shall provide drip
irrigation to new trees until they are established.
Building
Permit /
Ongoing
PS
Exhibit B Required Tree Removal Mitigation
PLN 2016-1616 / TRP 2016-0204
dbh tree number dbh tree number
1 12 570 1 12 575
2 16 573 2 7 576
3 30 582 3 6 577
4 12 586 4 8 585
5 7 591 5 4 589
6 24 592 6 10 596
7 22 593 7
8 33 594 8
9 5 595 9
10 10
11 11
12 12
13 13
14 14
15 15
Total 161 inches Total 47 inches 208
Mitigation Requirement
req'd tree replacements:27 five gal trees req'd tree replacements:16 five gal trees
Proposed Replanting 0 five gal trees Proposed Replanting 0 five gal trees 0 five gal trees
0 fifteen gal trees 0 fifteen gal trees 0 fifteen gal trees
0 box trees (24'')0 box trees (24'')0 box trees (24'')
Remaining Mitigation 27 five gal trees Remaining Mitigation 16 five gal trees 43 five gal trees
or or
Tree Fund Payment:1,341.67$ Tree Fund Payment:783.33$ 2,125.00$
Exhibit C Site Plan
PLN 2016-1616 / TRP 2016-0204
Bond payment for tree #31, impacted 45% :
570
592
591 589 586
585
582
577
576
575
573
593
594
596
595