Timing
FM: Final Map
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Agency
Requirement
FED: Federal Government
CAL: California
Government
LOC: Local Government
Standard Conditions
1. The approval of this use permit shall become final and effective
for the purposes of issuing building permits, provided the
required conditions of approval have been satisfied, fourteen (14)
days following the Planning Commission approval unless prior to
the time, an appeal to the decision is filed as set fort h in Section
9-1.111(b) of the Zoning Ordinance.
BP PS LOC
2. Approval of this Conditional Use Permit shall be valid for twenty –
four (24) months after its effective date. At the end of the period,
the approval shall expire and become null and void unless t he
applicant has received a building permit or applied for an
extension of entitlement.
BP PS LOC
3. The Community Development Department shall have the
authority to approve minor changes to the project that (1)
increase the square footage of the project by less than 10%, (2)
result in a superior site design or appearance, and/or (3) address
a construction design issue that is not substantive to the
Conditional Use Permit.
BP PS LOC
Project Conditions
4. All site design, landscaping, antenna / shelter placement, site
fencing, exterior elevations, finish materials and colors shall be
consistent with Exhibit C and Exhibit D.
BP/FO PS LOC
5. Cellular tower shall not exceed a height of 45-feet, measured
from the highest point of the structure to ground level, consistent
with Exhibit D
BP PS LOC
6. Cellular provider shall be limited to that area which is shown on
Exhibit C. Co-location for additional wireless carriers will be
required to obtain approval of a separate Conditional Use Permit
or as required by the Federal Communications Commission
(FCC).
On-Going PS LOC / FED
7. Proposed colors for cell phone tower must be consistent with
existing church colors and materials.
BP PS LOC
8. The proposed CMU wall shall encase the equipment shelter on
all sides with the exception of a gated fence. The gated fence
must use vinyl slats or other type of screening.
BP PS LOC
Conditions of Approval / Mitigation
Monitoring Program
PLN-2014-1524 / CUP-2014-0283
9685 Morro Road Cellular Facility
Timing
FM: Final Map
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Agency
Requirement
FED: Federal Government
CAL: California
Government
LOC: Local Government
9. Proposed color of CMU wall shall be consistent with the existing
architecture of the church facility and faux tower.
BP PS LOC
10. Lighting installations shall be consistent with the approved site
plan. No new light glare sources shall be permitted.
BP PS LOC
11. While Staff and the applicant have previously determined the
absence of hazardous materials on site via the Department of
Toxic Substances Control EnviroStor map, Staff will comply with
the Public Health’s Department request that the applicant provide
details on the levels of sulfuric acid, propane, and diesel fuel that
the new cellular facility could potentially produce. The thresholds
to be tested against will be the 200 cubic feet for propane and 55
gallons for diesel fuel and sulfuric acid. Details on the volumes of
the sulfuric acid onsite and how the volume of sulfuric acid was
calculated shall be provided. In the case that any one of these
toxic substances surpasses the thresholds stated, the applicant
will be required to submit a Hazardous Materials Business Plan
(HMBP) either via the state California Reporting System (CERS)
or through the local portal (www.ezsubmitsolgov.org). The
approval of the Conditional Use Permit (CUP) will be subject to
the completion of this request.
BP PS CAL
City Engineer Conditions
12. The applicant shall be responsible for the relocation and/or
alteration of existing utilities.
BP CE LOC / CAL
13. Prior to the issuance of building permits the applicant shall
submit a grading and drainage plan prepared by a registered civil
engineer for review and approval by the City Engineer, if
required.
BP CE LOC
14. Prior to the final inspection, the applicant shall submit a written
statement from a registered civil engineer that all work has been
completed and is in full compliance with the approved plans and
the California Building Code (CBC) prior to the final inspection, if
required.
FO CE LOC
Mitigation Monitoring Program 2015-0004
Mitigation Measure 3.b.1: The project shall be conditioned to comply
with all District regulations pertaining to the control of fugitive dust
(PM-10) as contained in Section 2 “Assessing and Mitigating
Construction Impacts.
BP BS/PS CAL
Mitigation Measure 3.b.2: The project shall be conditioned to comply
with all applicable APCD regulations pertaining to Naturally Occurring
Asbestos (NOA). Prior to any grading activities a geologic evaluation
should be conducted to determine if NOA is present within the area
that will be disturbed. If NOA is not present, and exemptions request
must be filed with the District. If NOA is found at the site, the applicant
BP BS/PS CAL
Conditions of Approval / Mitigation
Monitoring Program
PLN-2014-1524 / CUP-2014-0283
9685 Morro Road Cellular Facility
Timing
FM: Final Map
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Agency
Requirement
FED: Federal Government
CAL: California
Government
LOC: Local Government
must comply with all requirements outlined in the Asbestos ATCM.
This may include development of an Asbestos Dust Mitigation Plan
and an Asbestos Health and Safety program for approval by the
APCD. Technical Appendix 4.4 of the SLO County APCD CEQA Air
Quality Handbook includes a map of zones throughout San Luis
Obispo County where NOA has been found and geological evaluation
is required prior to any grading.
Mitigation 5.b.1: In the event that archaeological resources are
discovered on the property, all work on the project shall stop. When a
project will impact an archeological site, the Atascadero Community
Development Department shall first determine whether the site is a
historical resource. If a lead agency determines that the
archaeological site is an historical resource, it shall refer to the Public
Resources Code Sections for guidance. If an archaeological resource
is neither a unique archaeological nor an historical resource, the
effects of the project on those resources shall not be considered a
significant effect on the environment.
BP/GP PS/BS CAL
Mitigation 5.d.1: In the event that human remains are discovered on
the property, all work on the project shall stop a nd the Atascadero
Police Department and the County Coroner shall be contacted. The
Atascadero Community Development Department shall be notified. If
the human remains are identified as being Native American, the
California Native American Heritage Commission (NAHC) shall be
contacted at (916) 653-4082 within 24 hours. A representative from
both the Chumash Tribe and the Salinan Tribe shall be notified and
present during the excavation of any remains.
Ongoing PS CAL
Mitigation Measure 6.c.d.1: A soils report shall be required to be
submitted with a building permit by the building department. The
building plans will be required to follow the recommendations of the
soils report to assure safety for residents and buildings. The property
contains no unusual geological formations.
BP BS/PS CAL
Mitigation Measure 9.e.f.1: The developer is responsible for
ensuring that all contractors are aware of all storm water quality
measures and that such measures are implemented. Failure to
comply with the approved construction Best Management Practices
will result in the issuance of correction notices, citations, or stop
orders.
BP BS/PS CAL
Mitigation Measure 12.d.1: All construction activities shall comply
with the City of Atascadero Noise Ordinance for hours of operation.
BP BS/PS LOC
Mitigation Measure 16. e. The proposed cellular facility must be
consistent with Atascadero Fire Department Standards.
BP BS/PS LOC
EXHIBIT C: Overall Site Plan
PLN 2014-1524 / CUP 2014-0283 – 9685 Morro Road
EXHIBIT D: Proposed Elevations
PLN 2014-1524 / CUP 2014-0283 – 9685 Morro Road