Exhibit A: Tentative Parcel Map 2014-0102
Exhibit B: Conditions of Approval
Conditions of Approval
APN 049-045-022
805 El Camino Real
Tentative Parcel Map 2014-0102, Tract #AT14-0050
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Planning Services
1. The approval of this Tentative Parcel Map shall become final and effective
following approval of the 2015 amendment to CUP 2000-0014, Home Depot
center Master Plan of Development.
FM PS
2. Approval of this Tentative Parcel Map shall be valid for two years after its effective
date. At the end of the period, the approval shall expire and become null and void
unless a final map is recorded or an extension of time is granted pursuant to a
written request received prior to the expiration date.
FM
PS
3. The Community Development Department shall have the authority to approve
minor changes to the project that (1) result in a superior site design or
appearance, and/or (2) address a design issue that is not substantive to the
Tentative Parcel Map and that the Final Map is in substantial conformance with
the Tentative Map.
FM
PS
4. The granting of this entitlement shall apply to the property located at 805 El
Camino Real (APN 049-045-022) regardless of owner.
On going PS
5. The subdivider shall defend, indemnify, and hold harmless the City of Atascadero
or its agents, officers, and employees against any claim or action brought to
challenge an approval by the city, or any of its entities, concerning the
subdivision.
FM PS
6. The Final Map shall be drawn in substantial conformance with the approved
tentative map, and in compliance with all conditions set forth herein, shall be
submitted for review and approval in accordance with the Subdivision Map Act
and the City’s Subdivision Ordinance.
FM PS
Public Works Department Conditions
1. The applicant shall monument all property corners for construction control and
shall promptly replace them if disturbed.
FM PW
2. The applicant shall acquire title interest in any off-site land that may be required
to allow for the construction of the public improvements. The applicant shall
bear all costs associated with the necessary acquisitions. The applicant shall
also gain concurrence from all adjacent property owners whose ingress and
egress is affected by these improvements.
FM PW
3. Drainage easements shall be provided, as needed, to accommodate both
public and private drainage facilities.
FM PW
Conditions of Approval
APN 049-045-022
805 El Camino Real
Tentative Parcel Map 2014-0102, Tract #AT14-0050
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
4. The Final Map shall be acceptable to the City Surveyor or City Engineer prior to
the map being placed on the agenda for City acceptance.
FM PW
5. Prior to recording the parcel map, the applicant shall submit a map drawn in
substantial conformance with the approved tentative map and in compliance
with all conditions set forth herein. The map shall be submitted for review and
approval by the City in accordance with the Subdivision Map Act and the City's
Subdivision Ordinance.
FM PW
6. Prior to recording the parcel map, the applicant shall set monuments at all new
property corners. A registered civil engineer or licensed land surveyor shall
indicate by certificate on the parcel map, that corners have been set or shall be
set by a date specific and that they will be sufficient to enable the survey to be
retraced.
FM PW
7. Prior to recording the parcel map, the applicant shall pay all outstanding plan
check/inspection fees.
FM PW
8. Prior to recording the parcel map, the applicant shall have the map reviewed by
all applicable public and private utility companies (cable, telephone, gas,
electric, Atascadero Mutual Water Company). The applicant shall obtain a
letter from each utility company indicating their review of the map. The letter
shall identify any new easements that may be required by the utility company.
A copy of the letter shall be submitted to the City. New easements shall be
shown on the parcel map
FM PW
9. Prior to the issuance of building permits the applicant shall submit plans and
supporting calculations/reports including underground utilities, erosion control
and grading/drainage plans prepared by a registered civil engineer for review
and approval by the City Engineer.
GP / BP CE
10. Prior to the issuance of building permits the applicant shall submit calculations
to support the design of any storm water structures or pipes. Closed conduits
shall be designed to convey the 10-year flow with gravity flow, the 25-year flow
with head, and provide safe conveyance for the 100-year overflow. Storm water
collection system shall include provisions for capturing fuel spills using methods
acceptable to the Regional Water Quality Control Board.
GP / BP CE
11. Drainage basins or underground structures, if proposed, shall be designed to
desilt, detain and meter storm flows as well as release them to natural runoff
locations in accordance with the City of Atascadero Engineering Department
Standard Specifications and Drawings Section 5 or as directed by the City
Engineer.
GP / BP CE
12. Applicant shall submit a Storm Water Pollution Prevention Plan (SWPPP) if
greater than 1.0 acres is disturbed. The Regional Water Quality Control Board
shall approve the SWPPP.
GP / BP CE
13. All public improvements shall be constructed in conformance with the City of
Atascadero Engineering Department Standard Specifications and Drawings or
GP / BP CE
Conditions of Approval
APN 049-045-022
805 El Camino Real
Tentative Parcel Map 2014-0102, Tract #AT14-0050
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
as directed by the City Engineer
14. The applicant shall enter into a Plan Check / Inspection Agreement with the
City if required by the City Engineer.
GP / BP BD
15. The applicant shall be responsible for the relocation and/or alteration of all
existing utilities which interfere or conflict with proposed improvements.
GP / BP CE
16. The applicant shall install all new utilities underground. GP / BP CE
17. Prior to issuance of building permits the applicant shall pay all sewer
annexation and connection fees.
GP / BP CE
18. Prior to issuance of building permits the applicant shall submit a grading and
drainage plan prepared by a registered civil engineer for review and approval
by the City. All existing and proposed easements and all existing and
proposed utilities shall be shown on the plans.
GP CE
19. Prior to the final inspection, the applicant shall submit a written statement from
a registered civil engineer that all frontage improvement, grading and drainage
work has been completed and is in full compliance with the approved plans,
City Codes and Standards and the Uniform Building Code (UBC) as applicable.
FO CE
20. The applicant has submitted a project specific Traffic Study (Traffic Study).
The Traffic Study indicated that a traffic signal at the San Ramon El Camino
Real intersection was not warranted based on the cumulative + project +
existing traffic volumes. The City’s 2006 Master Facilities Plan and
Development Impact Fee Update Report identifies this intersection as being
signalized in the future. Therefore, a portion of this project’s Traffic Impact Fee
will be applied towards the eventual signalization of this intersection.
If project uses change from what is shown in the 2014 traffic report update,
then the installation of the signal shall be revisited and may be required to be
installed by the applicant.
Ongoing CE
21. Project applicant shall submit plans for the installation of a lighted crosswalk,
thermoplastic striping, and signage at the midblock crosswalk on El Camino
Real. Plans, equipment and specifications shall be acceptable to the City
Engineer prior to the issuance of an encroachment permit.
GP / BP CE
22. No structures shall be constructed over any storm drainage facilities or
easements.
BP CE
23. LID features such as bioswales shall be incorporated into the parking lot and
onsite frontage landscape areas as feasible to filter the run off drainage before
it leaves the site. The project shall comply with Section 5, Drainage, of the
City’s Standard Drawings and Specifications.
GP / BP CE