HomeMy WebLinkAboutPC Resolution 2014-0028Exhibit A: Tentative Tract Map (9 Unit PD-7)
Exhibit B: Conditions of Approval / Mitigation Monitoring Program
Tentative Tract Map 2007-0101
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Planning Services
1. The approval of this use permit shall become final and effective for the
purposes of issuing building permits thirty (30) days following the City
Council approval of ZCH 2007-140, ZCH 2007-0145 and ZCH 2007-
0146 upon second reading, unless prior to that time, an appeal to the
decision is filed as set forth in Section 9-1.111(b) of the Zoning
Ordinance.
FM PS
2. Approval of this Tentative Tract Map and Conditional Use Permit shall be
valid for two years after its effective date (February 26, 2008). At the end
of the period, the approval shall expire and become null and void unless
an extension of time is granted pursuant to a written request received
prior to the expiration date, or is granted extension through any State
legislation.
FM
PS
3. The Community Development Department shall have the authority to
approve minor changes to the project that (1) result in a superior site
design or appearance, and/or (2) address a design issue that is not
substantive to the Tentative Tract Map and that the Final Map is in
substantial conformance with the Tentative Map.
FM
PS
4. The granting of this entitlement shall apply to the property located at
(APN 030-283-005) regardless of owner.
On going PS
5. The Final Map shall be drawn in substantial conformance with the
approved tentative map, and in compliance with all conditions set forth
herein, shall be submitted for review and approval in accordance with the
Subdivision Map Act and the City’s Subdivision Ordinance.
FM PS
6. The subdivider shall defend, indemnify, and hold harmless the City of
Atascadero or its agents, officers, and employees against any claim or
action brought to challenge an approval by the city, or any of its entities,
concerning the subdivision.
FM PS
7. The Tract Map shall be subject to additional fees for park or recreation
purposes (QUIMBY Act) as required by City Ordinance.
FM
PS
8. The emergency services and facility maintenance costs listed below shall
be 100% funded by the project in perpetuity. The service and
maintenance costs shall be funded through a community facilities district
established by the City at the developer's cost. The funding mechanism
must be in place prior to or concurrently with acceptance of the final
maps. The funding mechanism shall be approved by the City Attorney,
City Engineer and Administrative Services Director prior to
BP PS
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
acceptance of any final map. The administration of the above
mentioned funds shall be by the City. Developer agrees to participate
in the community facilities district and to take all steps reasonably
required by the City with regard to the establishment of the district and
assessment of the property.
All Atascadero Police Department service costs to the project.
All Atascadero Fire Department service costs to the project.
Off-site common City of Atascadero park facilities maintenance
service costs related to the project.
9. All tract maintenance costs listed below shall be 100% funded by the
project / property in perpetuity.
All streets that are currently not maintained by the City of
Atascadero, bridges, sidewalks, streetlights, street signs, roads,
emergency access roads, emergency access gates, and sewer
mains within the project.
All parks, trails, recreational facilities and like facilities.
All open space and native tree preservation areas.
All drainage facilities and detention basins.
All creeks, flood plains, floodways, wetlands, and riparian
habitat areas.
All common landscaping areas, street trees, medians,
parkway planters, manufactured slopes outside private yards,
and other similar facilities.
All frontage landscaping and sidewalks along arterial streets
BP PS
10. The private open space feature at the corner of Atascadero Avenue and
San Andres shall be maintained by the property owner. All landscape
shall be maintained in good condition and the site shall be kept free of
litter and graffiti.
Ongoing PS
11. The developments approved with CUP 2007-0208 and CUP 2007-0219
shall be developed together as one Master Plan of Development at as
required by the General Plan.
BP / GP PS / PW
12. Prior to final map, the applicant shall submit CC&Rs for review and
approval by the Community Development Department. The CC&R’s
shall record with the Final Map and shall include the following
provisions within the CC&Rs:
1. Provisions for maintenance of all common areas including
access, parking, street trees, fencing and landscaping in
BP PS
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
perpetuity, if applicable.
2. Fencing design and locations
3. A detailed list of each individual homeowner’s responsibilities for
maintenance of the individual units.
4. Residents shall keep all trash receptacles within the unit’s
designated trash storage area.
5. Garages shall be maintained and used for vehicle parking.
6. No boats, RV’s or other type of recreation vehicle may occupy a
guest or resident parking space. including within an individual
garage.
7. A provision for review and approval by the City Community
Development Department for any changes to the CC&R’s that
relate to the above requirements prior to the changes being
recorded or taking effect.
13. Affordable Housing Requirement: As a General Plan required Master
Planned site (Master Plan of Development Overlay #12), the Affordable
Housing requirement shall apply to the 11 units approved for the subject
sites with ZCH 2007-0145 and ZCH 2007-0146.
The applicant shall deed restrict a minimum of 1 residential unit for 30
years, at the moderate income rate.
Exception to Affordable Housing Deed Restriction Requirement: The
City will not record 30 year recorded deed restrictions if the
developer can demonstrate that the project meets the following
criteria:
The project shall be developed as an entirely affordable
project, consisting of a mix of very low, low, or
moderate income units;
The housing units must be constructed with at least
50% of the work performed by volunteers and/or
households purchasing the housing;
The applicant must demonstrate that the home
purchase financing provided will be affordable to the
purchasing household for at least 30 years.
At least 1 moderate income unit shall be provided
within the project to meet the City Council Inclusionary
Housing policy.
GP/BP
PS, CA
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
14. Workforce Housing: Prior to recordation of final map, the applicant
shall enter into a legal agreement with the City to reserve ½ of the
units for sale to residents or workers within the City of Atascadero,
including the affordable units. The agreement shall include the
following provisions:
The units shall be offered for sale to residents or workers within
the City of Atascadero for a minimum of 60-days. During this
time period offers may only be accepted from Atascadero
residents or workers;
The applicant shall provide reasonable proof to the City that at
least one of the qualified buyers is a resident or worker within
the City Limits of Atascadero;
The Atascadero resident or worker restriction shall apply to the
initial sale only;
The applicant shall identify which units will be reserved; and
The City Attorney shall approve the final form of the agreement.
BP
PS, CE
15. Approval of this permit shall include the removal of 8 Native Black
Walnuts, totaling 310 inches dbh. The applicant shall be required to
pay mitigation fees or provide replantings on-site per the requirements
of the Atascadero Native Tree Ordinance. Any additional removals
shall be subject to Planning Commission approval.
BP PS, BS
16. The applicant shall work with staff to enhance the side elevation on Lot
8 facing Navajoa Avenue. The elevation shall include larger windows
and added architectural detailing, consistent with the front elevation.
Additional landscaping, including trees and tall shrubs shall be added
to the side setback on this lot. Fencing may not be located in the side
setback next to Navajoa Ave.
BP PS
17. The columns on the wrap around porch on floor plan D (shown in
Exhibits E and F) shall be a minimum size of 6” by 6” square. Railings
shall be added to the wrap around porch.
BP PS
18. All exterior elevations, finish materials and colors shall be consistent
with the Master Plan of Development as shown in EXHIBIT D and F
with the following modifications:
All exterior material finishes (siding, trim, doors, windows, light
fixtures, garage doors) shall be durable, high quality, and consistent
with the architectural appearance.
Stucco siding shall be smooth troweled or light sand finish.
Roofs shall be architectural grade dimensional shingles.
BP PS
19. Building colors shall be consistent with Exhibit G with the following
modification:
GP/BP PS
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
The color “clay urn” identified in color scheme #1 shall be replaced
with a more muted color, consistent with the surrounding residences
and color schemes 2 through 5.
Final selection of colors and materials shall be subject to staff approval.
20. Garage doors shall be high quality, wood or carriage style doors. BP PS
21. All site development shall comply with the standards of the Planned
Development 7 Overlay District.
BP PS, BS
22. All site work, grading, and site improvements shall be consistent with the
Master Plan of Development as shown in EXHIBIT B.
BP/FM PS, BS, CE
23. All project fencing shall be installed consistent throughout the project,
and located as shown in the approved Landscape Plan, subject to the
following modifications:
Fencing material and treatment shall comply with the PD-7
standards.
Final fence location shall be subject to staff approval.
Fencing within the front and corner lot setbacks shall be under 3
feet tall.
GP/BP
PS
24. A final landscape and irrigation plan shall be approved prior to the
issuance of building permits and included as part of site improvement
plan consistent with EXHIBIT J, and as follows:
All exterior meters, air conditioning units and mechanical
equipment shall be screened with landscape material.
All areas shown on the landscape plan shall be landscaped by the
developer prior to the final of any single building permit on-site.
Final tree list shall be submitted with building permits, subject to
staff approval.
Street and open space trees shall be minimum 15-gallon size and
double staked.
Front yard areas shall be landscaped with drought tolerant species,
subject to staff approval.
BP PS
25. The wall/fence around the private park on Lot 1 shall be allowed to be
built at a maximum height of 5 feet at the tallest point.
BP PS
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
26. The commemorative tile on the ‘commemorative wall” around he private
park on Lot 1 shall be subject to staff approval
BP PS
2014 Tentative Tract Map Amendments
27. Deed notification to be recorded at the time of Final Map
Recordation notifying all property owners within the project (CUP
2007-0219 / CUP 2007-0208) that maintenance responsibilities
include all landscaping within planting/parkway strips, front yard
landscaping including any trees, curbs, gutters, driveways and
sidewalks fronting a property are maintenance responsibilities of
the homeowners, not the City of Atascadero, consistent with
Atascadero Municipal Code section 4-6.04.
28. All Planning conditions of approval for the Master Plan of
Development (CUP 2007-0208) must be adhered to and is
incorporated via reference.
City Engineer Project Conditions
29. The applicant shall install curb, gutter and sidewalk along all property
frontages. All road frontages will be widened be City Standard.
GP, BP CE
30. This project is required to retain the difference between the undeveloped
2 year storm runoff and the developed 50 year storm runoff to mitigate
the increase runoff into the storm drain system. The project will use
individual drainage basin on each lot to handle the increased flow. The
basin will be underground “infiltrator” basins. Deep pit basins are not
allowed. When the basin becomes full, they will overflow into the new
curb and gutter through small drain pipe under the side walk.
31. The project engineer shall investigate the feasibility of installing 4 way
stop control on Navajoa at San Andres Ave and Atascadero Ave. The
engineer shall present a schematic layout of a 4 way stop and produce a
warrant analysis in accordance with the Manual on Uniform Traffic
Control Devices. The City Engineer shall decide if the 4 way stops shall
be installed based on the information submitted. Improvement cost
required by the warrant analysis shall be the responsibility of the City of
Atascadero.
GP, BP CE
32. In the event that the applicant bonds for the public improvements
required as a condition of this map, the applicant shall enter into a
Subdivision Improvement Agreement with the City Council.
GP, BP CE
33. An engineer’s estimate of probable cost shall be submitted for review
and approval by the City Engineer to determine the amount of the bond.
GP, BP CE
34. The Subdivision Improvement Agreement shall record concurrently with FM CE
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
the Final Map.
35. A six (6) foot Public Utility Easement (PUE) shall be provided contiguous
to the property frontage.
GP, BP CE
36. The applicant shall acquire title interest in any off-site land that may be
required to allow for the construction of the improvements. The applicant
shall bear all costs associated with the necessary acquisitions. The
applicant shall also gain concurrence from all adjacent property owners
whose ingress and egress is affected by these improvements.
GP, BP CE
37. Slope easements shall be obtained by the applicant as needed to
accommodate cut or fill slopes.
GP, BP CE
38. Drainage easements shall be obtained by the applicant as needed to
accommodate both public and private drainage facilities.
GP, BP CE
39. A preliminary subdivision guarantee shall be submitted for review in
conjunction with the processing of the tract map.
FM CE
40. The final map shall be signed by the City Engineer prior to the map
being placed on the agenda for City Council acceptance.
FM CE
41. Prior to recording the tract map, the applicant shall pay all outstanding
plan check/inspection fees.
FM CE
42. Prior to recording the map, the applicant shall bond for or complete all
improvements required by these conditions of approval.
FM CE
43. Prior to recording the tract map, the applicant shall submit a copy of a
valid tax bond.
FM CE
44. Prior to recording the tract map, the applicant shall bond for or set
monuments at all new property corners. A registered civil engineer or
licensed land surveyor shall indicate by certificate on the tract map, that
corners have been set or shall be set by a date specific and that they will
be sufficient to enable the survey to be retraced.
FM CE
45. Prior to recording the tract map, the applicant shall submit a map drawn
in substantial conformance with the approved tentative map and in
compliance with all conditions set forth herein. The map shall be
submitted for review and approval by the City in accordance with the
Subdivision Map Act and the City's Subdivision Ordinance.
FM CE
46. All existing and proposed utility, pipeline, open space, or other
easements are to be shown on the final map. If there are building or
other restrictions related to the easements, they shall be noted on the
FM CE
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
final map. The applicant shall show all access restrictions on the final
map.
47. Prior to recording the tract map, the applicant shall have the map
reviewed by all applicable public and private utility companies (cable,
telephone, gas, electric, Atascadero Mutual Water Company). The
applicant shall obtain a letter from each utility company indicating their
review of the map. The letter shall identify any new easements that
may be required by the utility company. A copy of the letter shall be
submitted to the City. New easements shall be shown on the tract map.
FM CE
48. Prior to the issuance of building permits the applicant shall submit plans
and supporting calculations/reports including street improvements,
underground utilities, composite utilities, and grading/drainage plans
prepared by a registered civil engineer for review and approval by the
City Engineer.
GP, BP CE
49. Prior to the issuance of building permits the applicant shall submit
calculations to support the design of any structures or pipes. Closed
conduits shall be designed to convey the 10-year flow with gravity flow,
the 25-year flow with head, and provide safe conveyance for the 100-
year overflow.
GP, BP CE
50. Prior to the issuance of building permits the applicant shall provide for
the detention and metering out of developed storm runoff so that it is
equal to or less than undeveloped storm runoff.
GP, BP CE
51. Drainage basins shall be designed to desilt, detain and meter storm
flows as well as release them to natural runoff locations.
GP, BP CE
52. All storm drain facilities servicing individual lots and units shall be
maintained by the property owner. A mechanism for funding and
maintenance of the storm drain facilities shall be provided for any
common area, or common storm drainage facility.
GP, BP CE
53. Prior to the issuance of building permits the applicant shall show the
method of dispersal at all pipe outlets. Include specifications for size &
type.
GP, BP CE
54. Prior to the issuance of building permits the applicant shall show method
of conduct to approved off-site drainage facilities.
GP, BP CE
55. Concentrated drainage from off-site areas shall be conveyed across the
project site in drainage easements. Acquire drainage easements where
needed. Drainage shall cross lot lines only where a drainage easement
has been provided. If drainage easement cannot be obtained the storm
water release must follow the exact historic path, rate and velocity as
prior to the subdivision.
GP, BP CE
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
56. Applicant shall submit erosion control plans and a Storm Water Pollution
Prevention Plan (SWPPP). The Regional Water Quality Control Board
shall approve the SWPPP.
GP, BP CE
57. All public improvements shall be constructed in conformance with the
City of Atascadero Engineering Department Standard Specifications and
Drawings or as directed by the City Engineer
GP, BP CE
58. Off-site streets shall be improved consistent with the tentative tract map. GP, BP CE
59. Project shall include construction of curb, gutter and sidewalk along
entire frontage.
GP, BP CE
60. Alignment of frontage improvements shall be approved by the City
Engineer.
GP, BP CE
61. All utilities shall be undergrounded on project frontage where feasible.
Existing poles may be preserved or moved on-site to avoid
additional installation of guide poles off-site. Applicant shall work
with City Staff to minimize the amount of poles required on-site.
GP, BP CE
62. Applicant shall pay sewer extension (Annexation), Connection and
Reimbursement fees (if applicable) upon issuance of building permit.
BP CE
63. Drainage piping serving fixtures which have flood level rims located
below the elevation of the next upstream manhole cover of the public or
private sewer serving such drainage piping shall be protected from
backflow of sewage by installing an approved type backwater valve.
Fixtures above such elevation shall not discharge through the backwater
valve.
BP CE
Mitigation Measures
Mitigation Measure 3.b.1: The project shall be conditioned to comply with all
applicable District regulations pertaining to the control of fugitive dust (PM-
10) as contained in sections 6.3, 6.4 and 6.5 of the April 2003 Air Quality
Handbook.
Section 6.3: Construction Equipment
Maintain all construction equipment in proper tune according to
manufacturer’s specifications.
Fuel all off-road and portable diesel powered equipment, including
but not limited to bulldozers, graders, cranes, loaders, scrapers,
backhoes, generator sets, compressors, auxiliary power units, with
ARB certified motor vehicle diesel fuel (Non-taxed version suitable
for use off-road).
Maximize to the extent feasible, the use of diesel construction
equipment meeting the ARB’s 1996 or newer certification standard
for off-road heavy-duty diesel engines.
BP BS/PS 3.b.1
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Section 6.4: Activity Management Techniques
Develop a comprehensive construction activity managem ent plan
designed to minimize the amount of large construction equipment
operating during any given time period.
Schedule of construction truck trips during non-peak hours to
reduce peak hour emissions.
Limit the length of the construction workday period, if necessary.
Phase construction activities, if appropriate.
Section 6.5: Fugitive PM10
All of the following measures shall be included on grading, demolition and
building plan notes:
A. Reduce the amount of the disturbed area where possible.
B. Use of water trucks or sprinkler systems in sufficient quantities to
prevent airborne dust from leaving the site. Increased watering
frequency would be required whenever wind speeds exceed 15 mph.
Reclaimed (non-potable) water should be used whenever possible.
C. All dirt stockpile areas should be sprayed daily as needed.
D. Permanent dust control measures identified in the approved project re -
vegetation and landscape plans should be implemented as soon as
possible following completion of any soil disturbing activities.
E. Exposed ground areas that are planned to be reworked at dates greater
than one month after initial grading should be sown with a fast-
germinating native grass seed and watered until vegetation is
established.
F. All disturbed soil areas not subject to re-vegetation should be stabilized
using approved chemical soil binder, jute netting, or other methods
approved in advance by the APCD.
G. All roadways, driveways, sidewalks, etc, to be paved should be
complete as soon as possible. In addition, building pads should be laid
as soon as possible after grading unless seeding or soil binders are
used.
H. Vehicle speed for all construction vehicles shall not exceed 15 mph on
any unpaved surface at the construction site.
I. All trucks hauling dirt, sand, soil, or other loose materials are to be
covered or should maintain at least two feet of freeboard (minimum
vertical distance between top of load and top of trailer) in accordance
with CVC Section 23114.
J. Install wheel washers where vehicles enter and exit unpaved roads onto
streets, or wash off trucks and equipment leaving the site.
K. Sweep streets at the end of each day if visible soil material is carried
onto adjacent paved roads. Water sweepers with reclaimed water
should be used where feasible.
L. The contractor or builder shall designate a person or persons to monitor
the dust control program and to order increased watering, as necessary,
to prevent transport of dust off site. The name and telephone number of
such persons shall be provided to the APCD prior to land use clearance
for map recordation and land use clearance for finish grading of any
structure.
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Mitigation Measure 3.b.2: The project shall be conditioned to comply with all
applicable APCD regulations pertaining to Naturally Occurring Asbestos.
Prior to any grading activities at the site, the project proponent shall ensure
that a geologic evaluation is conducted to determine if NOA is present within
the area that will be disturbed. If NOA is not present, an exemption request
must be filed with the District (see Attachment 1). If NOA is found at the site
the applicant must comply with all requirements outlined in the Asbestos
ATCM. This may include development of an Asbestos Dust Mitigation Plan
and an Asbestos Health and Safety Program for approval by the APCD.
Refer to the APCD web page at
http://www.slocleanair.org/business/asbestos.asp for more information or
contact Tim Fuhs of the Enforcement Division at 781-5912.
BP BS/PS 3.b.2
Mitigation Measure 3.b.3: Developmental burning of vegetative material is
prohibited. Under certain circumstances where no technically feasible
alternatives are available, limited developmental burning under restrictions
may be allowed. This requires prior application, payment of fee based on
the size of the project, APCD approval, and issuance of a burn permit by the
APCD and the local fire department authority. The applicant is required to
furnish the APCD with the study of technical feasibility (which includes costs
and other constraints) at the time of application. For any questions
regarding these requirements, contact Karen Brooks of the Enforcement
Division at 781-5912.
BP BS/PS 3.b.3
Mitigation Measure 3.b.4: Under APCD Rule 504, only APCD approved
wood burning devices can be installed in new dwelling units. These devices
include:
All EPA-Certified Phase II wood burning devices;
Catalytic wood burning devices which emit less than or equal to 4.1
grams per hour of particulate matter which are not EPA-Certified
but have been verified by a nationally-recognized testing lab;
Non-catalytic wood burning devices which emit less than or equal
to 7.5 grams per hour of particulate matter which are not EPA-
Certified but have been verified by a nationally-recognized testing
lab;
Pellet-fueled woodheaters; and
Dedicated gas-fired fireplaces.
Questions about approved wood burning devices, should be refered to Tim
Fuhs in the Enforcement Division at 781-5912.
BP BS/PS 3.b.4
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Mitigation Measure 4.e.1: The developer shall contract with a certified
arborist during all phases of project implementation. The certified arborists
shall be responsible for monitoring the project during all phases of
construction through project completion, as follows:
(a) A written agreement between the arborist and the developer outlining
an arborist monitoring schedule for each construction phase through
final inspection shall be submitted to and approved by planning staff
prior to the issuance of building/grading permits.
(b) Arborist shall schedule a pre-construction meeting with engineering
/planning staff, grading equipment operators, project superintendent to
review the project conditions and requirements prior to any grubbing or
earth work for any portion of the project site. All tree protectio n fencing
and trunk protection shall be installed for inspection during the meeting.
Tree protection fencing shall be installed at the line of encroachment
into the tree’s root zone area.
(c) As specified by the arborist report and City staff:
Prune all trees in active development areas to be saved for
structural strength and crown cleaning by a licensed and certified
arborist;
Remove all debris and spoils from the lot cleaning and tree pruning.
In locations where paving is to occur within the tree canopy, grub
only and do not grade nor compact. Install porous pavers over a
three-inch bed of ¾ inch granite covered with one-inch pea gravel
for screeding. If curbs are required, use pegged curbs to secure the
porous pavers. Pegged curbs are reinforced six to eight curbs
poured at grade with a one-foot by one-foot pothole every four to six
linear feet.
All trenching or grading within the protected root zone area, outside
of the tree protection fence shall require hand trenching or preserve
and protect roots that are larger than 2 inches in diameter.
No grading or trenching is allowed within the fenced protected area.
Any roots that are 4 inches in diameter or larger are not to be cut
until inspected and approved by the on-site arborist.
(d) Upon project completion and prior to final occupancy a final status
report shall be prepared by the project arborist certifying that the tree
protection plan was implemented, the trees designated for protection
were protected during construction, and the construction-related tree
protection measures are no longer required for tree protection.
BP BS/PS 4.e.1
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Mitigation Measure 4.e.2:
1. All existing trees outside of the limits of work shall remain.
2. Earthwork shall not exceed the limits of the project area.
3. Low branches in danger of being torn from trees shall be pruned
prior to any heavy equipment work being done.
4. Vehicles and stockpiled material shall be stored outside the drip
line of all trees.
5. All trees within twenty feet of construction work shall be fenced for
protection with 4-foot chain link, snow or safety fencing placed per
the approved tree protection plan. Tree protection fencing shall be
in place prior to any site excavation or grading. Fencing shall
remain in place until completion of all construction activities.
6. Any roots that are encountered during excavation shall be clean cut
by hand and sealed with an approved tree seal.
7. Utilities such as water, gas, power, cable, storm drainage, and
sewer should be redirected from under the canopy of any trees that
are to remain.
8. Where a building is placed within the canopy of a tree the
foundation should be redesigned so that it bridges across any root
systems.
9. Any foundation or other structure that encroaches within the drip
line of trees to be saved shall be dug by hand.
10. At no time shall tree roots be ripped with construction equipment.
BP BS/PS 4.e.2
Mitigation 5.d.1: Should any human remains be discovered on the property,
all work on the project should stop and the County Coroner contacted. If the
human remains are identified as being Native American, the California
Native American Heritage Commission (NAHC) should be contacted at
(916) 653-4082.
Ongoing PS 5.d.1
Mitigation Measure 6.b.1: All cut and fill slopes shall be hydro seeded with
an appropriate erosion control method (erosion control blanket, hydro -
mulch, or straw mulch appropriately anchored) immediately after completion
of earthwork between the months of October 15 through April 15. All
hydroseed mix shall be native species. All disturbed slopes shall have
appropriate erosion control methods in place. Duration of the project: The
contractor will be responsible for the clean-up of any mud or debris that is
tracked onto public streets by construction vehicles.
BP BS/PS 6.b.1
Mitigation Measure 8.e.f.1: The developer is responsible for ensuring that
all contractors are aware of all storm water quality measures and that such
measures are implemented. Failure to comply with the approved
construction Best Management Practices will result in the issuance of
correction notices, citations, or stop orders.
BP BS/PS 8.e.f.1
Mitigation Measure 11.d.1: All construction activities shall comply with the
City of Atascadero Noise Ordinance for hours of operation.
BP BS/PS 11.d.1
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0028.docx