EXHIBIT A: Conditions of Approval / Mitigation Monitoring Program
9-unit Planned Development-7 /CUP 2007-0157/ZCH 2007-0145/TTM 2007-0101
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Planning Services
1. The approval of this use permit shall become final and effective for the
purposes of issuing building permits thirty (30) days following the City Council
approval of ZCH 2007-140, ZCH 2007-0145 and ZCH 2007-0146 upon
second reading, unless prior to that time, an appeal to the decision is filed as
set forth in Section 9-1.111(b) of the Zoning Ordinance.
FM PS
2. Approval of this Tentative Tract Map and Conditional Use Permit shall be valid
for two years after its effective date (February 26, 2008). At the end of the
period, the approval shall expire and become null and void unless an
extension of time is granted pursuant to a written request received prior to the
expiration date, or is granted extension through any State legislation.
FM
PS
3. The Community Development Department shall have the authority to approve
minor changes to the project that (1) result in a superior site design or
appearance, and/or (2) address a design issue that is not substantive to the
Tentative Tract Map and that the Final Map is in substantial conformance with
the Tentative Map.
FM
PS
4. The granting of this entitlement shall apply to the property located at (APN
030-283-005) regardless of owner.
On going PS
5. The Final Map shall be drawn in substantial conformance with the approved
tentative map, and in compliance with all conditions set forth herein, shall be
submitted for review and approval in accordance with the Subdivision Map Act
and the City’s Subdivision Ordinance.
FM PS
6. The subdivider shall defend, indemnify, and hold harmless the City of
Atascadero or its agents, officers, and employees against any claim or action
brought to challenge an approval by the city, or any of its entities, concerning
the subdivision.
FM PS
7. The Tract Map shall be subject to additional fees for park or recreation
purposes (QUIMBY Act) as required by City Ordinance.
FM
PS
8. The emergency services and facility maintenance costs listed below shall
be 100% funded by the project in perpetuity. The service and maintenance
costs shall be funded through a community facilities district established by
the City at the developer's cost. The funding mechanism must be in place
prior to or concurrently with acceptance of the final maps. The funding
mechanism shall be approved by the City Attorney, City Engineer and
Administrative Services Director prior to acceptance of any final map. The
BP PS
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
administration of the above mentioned funds shall be by the City.
Developer agrees to participate in the community facilities district and to
take all steps reasonably required by the City with regard to the
establishment of the district and assessment of the property.
All Atascadero Police Department service costs to the project.
All Atascadero Fire Department service costs to the project.
Off-site common City of Atascadero park facilities maintenance service
costs related to the project.
9. All tract maintenance costs listed below shall be 100% funded by the project /
property in perpetuity.
All streets that are currently not maintained by the City of
Atascadero, bridges, sidewalks, streetlights, street signs, roads,
emergency access roads, emergency access gates, and sewer
mains within the project.
All parks, trails, recreational facilities and like facilities.
All open space and native tree preservation areas.
All drainage facilities and detention basins.
All creeks, flood plains, floodways, wetlands, and riparian habitat
areas.
All common landscaping areas, street trees, medians, parkway
planters, manufactured slopes outside private yards, and other
similar facilities.
All frontage landscaping and sidewalks along arterial streets
BP PS
10. The private open space feature at the corner of Atascadero Avenue and San
Andres shall be maintained by the property owner. All landscape shall be
maintained in good condition and the site shall be kept free of litter and graffiti.
Ongoing PS
11. The developments approved with CUP 2007-0208 and CUP 2007-0219 shall
be developed together as one Master Plan of Development at as required by
the General Plan.
BP / GP PS / PW
12. Prior to final map, the applicant shall submit CC&Rs for review and approval
by the Community Development Department. The CC&R’s shall record with
the Final Map and shall include the following provisions within the CC&Rs:
1. Provisions for maintenance of all common areas including access,
parking, street trees, fencing and landscaping in perpetuity, if
applicable.
BP PS
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
2. Fencing design and locations
3. A detailed list of each individual homeowner’s responsibilities for
maintenance of the individual units.
4. Residents shall keep all trash receptacles within the unit’s
designated trash storage area.
5. Garages shall be maintained and used for vehicle parking.
6. No boats, RV’s or other type of recreation vehicle may occupy a
guest or resident parking space. including within an individual
garage.
7. A provision for review and approval by the City Community
Development Department for any changes to the CC&R’s that relate
to the above requirements prior to the changes being recorded or
taking effect.
13. Affordable Housing Requirement: As a General Plan required Master
Planned site (Master Plan of Development Overlay #12), the Affordable
Housing requirement shall apply to the 11 units approved for the subject sites
with ZCH 2007-0145 and ZCH 2007-0146.
The applicant shall deed restrict a minimum of 1 residential unit for 30 years,
at the moderate income rate.
Exception to Affordable Housing Deed Restriction Requirement: The
City will not record 30 year recorded deed restrictions if the developer
can demonstrate that the project meets the following criteria:
The project shall be developed as an entirely affordable
project, consisting of a mix of very low, low, or moderate
income units;
The housing units must be constructed with at least 50% of
the work performed by volunteers and/or households
purchasing the housing;
The applicant must demonstrate that the home purchase
financing provided will be affordable to the purchasing
household for at least 30 years.
At least 1 moderate income unit shall be provided within
the project to meet the City Council Inclusionary Housing
policy.
GP/BP
PS, CA
14. Workforce Housing: Prior to recordation of final map, the applicant shall enter
into a legal agreement with the City to reserve ½ of the units for sale to
residents or workers within the City of Atascadero, including the affordable
BP
PS, CE
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
units. The agreement shall include the following provisions:
The units shall be offered for sale to residents or workers within the City of
Atascadero for a minimum of 60-days. During this time period offers may
only be accepted from Atascadero residents or workers;
The applicant shall provide reasonable proof to the City that at least one
of the qualified buyers is a resident or worker within the City Limits of
Atascadero;
The Atascadero resident or worker restriction shall apply to the initial sale
only;
The applicant shall identify which units will be reserved; and
The City Attorney shall approve the final form of the agreement.
15. Approval of this permit shall include the removal of 8 Native Black Walnuts,
totaling 310 inches dbh. The applicant shall be required to pay mitigation fees
or provide replantings on-site per the requirements of the Atascadero Native
Tree Ordinance. Any additional removals shall be subject to Planning
Commission approval.
BP PS, BS
16. The applicant shall work with staff to enhance the side elevation on Lot 8
facing Navajoa Avenue. The elevation shall include larger windows and added
architectural detailing, consistent with the front elevation. Additional
landscaping, including trees and tall shrubs shall be added to the side setback
on this lot. Fencing may not be located in the side setback next to Navajoa
Ave.
BP PS
17. The columns on the wrap around porch on floor plan D (shown in Exhibits E
and F) shall be a minimum size of 6” by 6” square. Railings shall be added to
the wrap around porch.
BP PS
18. All exterior elevations, finish materials and colors shall be consistent with the
Master Plan of Development as shown in EXHIBIT D and F with the following
modifications:
All exterior material finishes (siding, trim, doors, windows, light fixtures,
garage doors) shall be durable, high quality, and consistent with the
architectural appearance.
Stucco siding shall be smooth troweled or light sand finish.
Roofs shall be architectural grade dimensional shingles.
BP PS
19. Building colors shall be consistent with Exhibit G with the following
modification:
The color “clay urn” identified in color scheme #1 shall be replaced with a
more muted color, consistent with the surrounding residences and color
schemes 2 through 5.
GP/BP
PS
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
Final selection of colors and materials shall be subject to staff approval.
20. Garage doors shall be high quality, wood or carriage style doors of
architectural grade quality.
BP PS
21. All site development shall comply with the standards of the Planned
Development 7 Overlay District.
BP PS, BS
22. All site work, grading, and site improvements shall be consistent with the
Master Plan of Development as shown in EXHIBIT B.
BP/FM PS, BS, CE
23. All project fencing shall be installed consistent throughout the project, and
located as shown in the approved Landscape Plan, subject to the following
modifications:
Fencing material and treatment shall comply with the PD-7 standards.
Final fence location shall be subject to staff approval.
Fencing within the front and corner lot setbacks shall be under 3 feet
tall.
Fencing within Lot 1 and Lot 2 of CUP 2007-0219 shall consists of
wood picket / vinyl picket fencing.
GP/BP
PS
24. A final landscape and irrigation plan shall be approved prior to the issuance of
building permits and included as part of site improvement plan consistent with
EXHIBIT J, and as follows:
All exterior meters, air conditioning units and mechanical equipment
shall be screened with landscape material.
All areas shown on the landscape plan shall be landscaped by the
developer prior to the final of any single building permit on-site.
Final tree list shall be submitted with building permits, subject to staff
approval.
Street and open space trees shall be minimum 15-gallon size and
double staked.
Front yard areas shall be landscaped with drought tolerant species or
utilize xeriscape landscaping, subject to staff approval.
Street Tree Plantings within the “parkway” strip must consist of
California Sycamore Trees, minimum 15-gallon plantings. These
plantings may be used to reduce tree removal mitigation
payments.
BP PS
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
A minimum of four (4) native tree plantings must occur within the
Front / Side Yard landscaping of Lot 1 and Lot 2of CUP 2007-0219.
These plantings may be used to reduce tree removal mitigation
payments.
25. The wall/fence around the private park on Lot 1 shall be allowed to be built at
a maximum height of 5 feet at the tallest point.
BP PS
26. The commemorative tile on the ‘commemorative wall” around he private park
on Lot 1 shall be subject to staff approval
BP PS
2014 Master Plan of Amendment Conditions
27. Deed notification to be recorded at the time of Final Map Recordation
notifying all property owners within the project (CUP 2007-0219 / CUP
2007-0208) that maintenance responsibilities include all landscaping
within planting/parkway strips, front yard landscaping including any
trees, curbs, gutters, driveways and sidewalks fronting a property are
maintenance responsibilities of the homeowners, not the City of
Atascadero, consistent with Atascadero Municipal Code section 4-6.04.
FM PS
City Engineer Project Conditions
28. The applicant shall install curb, gutter and sidewalk along all property
frontages. All road frontages will be widened be City Standard.
BP CE
29. This project is required to retain the difference between the undeveloped 2
year storm runoff and the developed 50 year storm runoff to mitigate the
increase runoff into the storm drain system. The project will use individual
drainage basin on each lot to handle the increased flow. The basin will be
underground “infiltrator” basins. Deep pit basins are not allowed. When the
basin becomes full, they will overflow into the new curb and gutter through
small drain pipe under the side walk.
GP, BP CE
30. The project engineer shall investigate the feasibility of installing 4 way stop
control on Navajoa at San Andres Ave and Atascadero Ave. The engineer
shall present a schematic layout of a 4 way stop and produce a warrant
analysis in accordance with the Manual on Uniform Traffic Control Devices.
The City Engineer shall decide if the 4 way stops shall be ins talled based
on the information submitted. Improvement cost required by the warrant
analysis shall be the responsibility of the City of Atascadero.
GP, BP CE
City Engineer Standard Conditions
31. In the event that the applicant bonds for the public improvements required as
a condition of this map, the applicant shall enter into a Subdivision
Improvement Agreement with the City Council.
GP, BP CE
32. An engineer’s estimate of probable cost shall be submitted for review and GP, BP CE
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
approval by the City Engineer to determine the amount of the bond.
33. The Subdivision Improvement Agreement shall record concurrently with the
Final Map.
FM CE
34. A six (6) foot Public Utility Easement (PUE) shall be provided contiguous to
the property frontage.
GP, BP CE
35. The applicant shall acquire title interest in any off-site land that may be
required to allow for the construction of the improvements. The applicant shall
bear all costs associated with the necessary acquisitions. The applicant shall
also gain concurrence from all adjacent property owners whose ingress and
egress is affected by these improvements.
GP, BP CE
36. Slope easements shall be obtained by the applicant as needed to
accommodate cut or fill slopes.
GP, BP CE
37. Drainage easements shall be obtained by the applicant as needed to
accommodate both public and private drainage facilities.
GP, BP CE
38. A preliminary subdivision guarantee shall be submitted for review in
conjunction with the processing of the tract map.
FM CE
39. The final map shall be signed by the City Engineer prior to the map being
placed on the agenda for City Council acceptance.
FM CE
40. Prior to recording the tract map, the applicant shall pay all outstanding plan
check/inspection fees.
FM CE
41. Prior to recording the map, the applicant shall bond for or complete all
improvements required by these conditions of approval.
FM CE
42. Prior to recording the tract map, the applicant shall submit a copy of a valid tax
bond.
FM CE
43. Prior to recording the tract map, the applicant shall bond for or set monuments
at all new property corners. A registered civil engineer or licensed land
surveyor shall indicate by certificate on the tract map, that corners have been
set or shall be set by a date specific and that they will be sufficient to enable
the survey to be retraced.
FM CE
44. Prior to recording the tract map, the applicant shall submit a map drawn in
substantial conformance with the approved tentative map and in compliance
with all conditions set forth herein. The map shall be submitted for review and
approval by the City in accordance with the Subdivision Map Act and the
City's Subdivision Ordinance.
FM CE
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
45. All existing and proposed utility, pipeline, open space, or other easements are
to be shown on the final map. If there are building or other restrictions related
to the easements, they shall be noted on the final map. The applicant shall
show all access restrictions on the final map.
FM CE
46. Prior to recording the tract map, the applicant shall have the map reviewed by
all applicable public and private utility companies (cable, telephone, gas,
electric, Atascadero Mutual Water Company). The applicant shall obtain a
letter from each utility company indicating their review of the map. The letter
shall identify any new easements that may be required by the utility company.
A copy of the letter shall be submitted to the City. New easements shall be
shown on the tract map.
FM CE
47. Prior to the issuance of building permits the applicant shall submit plans and
supporting calculations/reports including street improvements, underground
utilities, composite utilities, and grading/drainage plans prepared by a
registered civil engineer for review and approval by the City Engineer.
GP, BP CE
48. Prior to the issuance of building permits the applicant shall submit calculations
to support the design of any structures or pipes. Closed conduits shall be
designed to convey the 10-year flow with gravity flow, the 25-year flow with
head, and provide safe conveyance for the 100-year overflow.
GP, BP CE
49. Prior to the issuance of building permits the applicant shall provide for the
detention and metering out of developed storm runoff so that it is equal to or
less than undeveloped storm runoff.
GP, BP CE
50. Drainage basins shall be designed to desilt, detain and meter storm flows as
well as release them to natural runoff locations.
GP, BP CE
51. All storm drain facilities servicing individual lots and units shall be
maintained by the property owner. A mechanism for funding and
maintenance of the storm drain facilities shall be provided for any common
area, or common storm drainage facility.
GP, BP CE
52. Prior to the issuance of building permits the applicant shall show the method
of dispersal at all pipe outlets. Include specifications for size & type.
GP, BP CE
53. Prior to the issuance of building permits the applicant shall show method of
conduct to approved off-site drainage facilities.
GP, BP CE
54. Concentrated drainage from off-site areas shall be conveyed across the
project site in drainage easements. Acquire drainage easements where
needed. Drainage shall cross lot lines only where a drainage easement has
been provided. If drainage easement cannot be obtained the storm water
release must follow the exact historic path, rate and velocity as prior to the
subdivision.
GP, BP CE
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
55. Applicant shall submit erosion control plans and a Storm Water Pollution
Prevention Plan (SWPPP). The Regional Water Quality Control Board shall
approve the SWPPP.
GP, BP CE
56. All public improvements shall be constructed in conformance with the City of
Atascadero Engineering Department Standard Specifications and Drawings or
as directed by the City Engineer
GP, BP CE
57. Off-site streets shall be improved consistent with the tentative tract map. GP, BP CE
58. Project shall include construction of curb, gutter and sidewalk along entire
frontage.
GP, BP CE
59. Alignment of frontage improvements shall be approved by the City Engineer. GP, BP CE
60. All utilities shall be undergrounded on project frontage where feasible.
Existing poles may be preserved or moved on-site to avoid additional
installation of guide poles off-site. Applicant shall work with City Staff to
minimize the amount of poles required on-site.
GP, BP CE
61. Applicant shall pay sewer extension (Annexation), Connection and
Reimbursement fees (if applicable) upon issuance of building permit.
BP CE
62. Drainage piping serving fixtures which have flood level rims located below the
elevation of the next upstream manhole cover of the public or private sewer
serving such drainage piping shall be protected from backflow of sewage by
installing an approved type backwater valve. Fixtures above such elevation
shall not discharge through the backwater valve.
BP CE
Mitigation Measures
Mitigation Measure 3.b.1: The project shall be conditioned to comply with all
applicable District regulations pertaining to the control of fugitive dust (PM-10)
as contained in sections 6.3, 6.4 and 6.5 of the April 2003 Air Quality
Handbook.
Section 6.3: Construction Equipment
Maintain all construction equipment in proper tune according to
manufacturer’s specifications.
Fuel all off-road and portable diesel powered equipment, including but
not limited to bulldozers, graders, cranes, loaders, scrapers, backhoes,
generator sets, compressors, auxiliary power units, with ARB certified
motor vehicle diesel fuel (Non-taxed version suitable for use off-road).
Maximize to the extent feasible, the use of diesel construction
equipment meeting the ARB’s 1996 or newer certification standard for
off-road heavy-duty diesel engines.
Section 6.4: Activity Management Techniques
Develop a comprehensive construction activity management plan
BP BS/PS 3.b.1
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
designed to minimize the amount of large construction equipment
operating during any given time period.
Schedule of construction truck trips during non-peak hours to reduce
peak hour emissions.
Limit the length of the construction workday period, if necessary.
Phase construction activities, if appropriate.
Section 6.5: Fugitive PM10
All of the following measures shall be included on grading, demolition and
building plan notes:
A. Reduce the amount of the disturbed area where possible.
B. Use of water trucks or sprinkler systems in sufficient quantities to prevent
airborne dust from leaving the site. Increased watering frequency would be
required whenever wind speeds exceed 15 mph. Reclaimed (non-potable)
water should be used whenever possible.
C. All dirt stockpile areas should be sprayed daily as needed.
D. Permanent dust control measures identified in the approved project re -
vegetation and landscape plans should be implemented as soon as
possible following completion of any soil disturbing activities.
E. Exposed ground areas that are planned to be reworked at dates greater
than one month after initial grading should be sown with a fast-germinating
native grass seed and watered until vegetation is established.
F. All disturbed soil areas not subject to re-vegetation should be stabilized
using approved chemical soil binder, jute netting, or other methods
approved in advance by the APCD.
G. All roadways, driveways, sidewalks, etc, to be paved should be complete
as soon as possible. In addition, building pads should be laid as soon as
possible after grading unless seeding or soil binders are used.
H. Vehicle speed for all construction vehicles shall not exceed 15 mph on any
unpaved surface at the construction site.
I. All trucks hauling dirt, sand, soil, or other loose materials are to be covered
or should maintain at least two feet of freeboard (minimum vertical distance
between top of load and top of trailer) in accordance with CVC Section
23114.
J. Install wheel washers where vehicles enter and exit unpaved roads onto
streets, or wash off trucks and equipment leaving the site.
K. Sweep streets at the end of each day if visible soil material is carried onto
adjacent paved roads. Water sweepers with reclaimed water should be
used where feasible.
L. The contractor or builder shall designate a person or persons to monitor the
dust control program and to order increased watering, as necessary, to
prevent transport of dust off site. The name and telephone number of such
persons shall be provided to the APCD prior to land use clearance for map
recordation and land use clearance for finish grading of any structure.
Mitigation Measure 3.b.2: The project shall be conditioned to comply with all
applicable APCD regulations pertaining to Naturally Occurring Asbestos. Prior
to any grading activities at the site, the project proponent shall ensure that a
geologic evaluation is conducted to determine if NOA is present within the area
BP BS/PS 3.b.2
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
that will be disturbed. If NOA is not present, an exemption request must be filed
with the District (see Attachment 1). If NOA is found at the site the applicant
must comply with all requirements outlined in the Asbestos ATCM. This may
include development of an Asbestos Dust Mitigation Plan and an Asbestos
Health and Safety Program for approval by the APCD. Refer to the APCD web
page at http://www.slocleanair.org/business/asbestos.asp for more information
or contact Tim Fuhs of the Enforcement Division at 781-5912.
Mitigation Measure 3.b.3: Developmental burning of vegetative material is
prohibited. Under certain circumstances where no technically feasible
alternatives are available, limited developmental burning under restrictions may
be allowed. This requires prior application, payment of fee based on the size of
the project, APCD approval, and issuance of a burn permit by the APCD and
the local fire department authority. The applicant is required to furnish the
APCD with the study of technical feasibility (which includes costs and other
constraints) at the time of application. For any questions regarding these
requirements, contact Karen Brooks of the Enforcement Division at 781-5912.
BP BS/PS 3.b.3
Mitigation Measure 3.b.4: Under APCD Rule 504, only APCD approved wood
burning devices can be installed in new dwelling units. These devices include:
All EPA-Certified Phase II wood burning devices;
Catalytic wood burning devices which emit less than or equal to 4.1
grams per hour of particulate matter which are not EPA-Certified but
have been verified by a nationally-recognized testing lab;
Non-catalytic wood burning devices which emit less than or equal to
7.5 grams per hour of particulate matter which are not EPA-Certified
but have been verified by a nationally-recognized testing lab;
Pellet-fueled woodheaters; and
Dedicated gas-fired fireplaces.
Questions about approved wood burning devices, should be refered to Tim
Fuhs in the Enforcement Division at 781-5912.
BP BS/PS 3.b.4
Mitigation Measure 4.e.1: The developer shall contract with a certified arborist
during all phases of project implementation. The certified arborists shall be
responsible for monitoring the project during all phases of construction through
project completion, as follows:
(a) A written agreement between the arborist and the develope r outlining a
arborist monitoring schedule for each construction phase through final
inspection shall be submitted to and approved by planning staff prior to the
issuance of building/grading permits.
(b) Arborist shall schedule a pre-construction meeting with engineering
/planning staff, grading equipment operators, project superintendent to
review the project conditions and requirements prior to any grubbing or
earth work for any portion of the project site. All tree protection fencing and
trunk protection shall be installed for inspection during the meeting. Tree
protection fencing shall be installed at the line of encroachment into the
BP BS/PS 4.e.1
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
tree’s root zone area.
(c) As specified by the arborist report and City staff:
Prune all trees in active development areas to be saved for structural
strength and crown cleaning by a licensed and certified arborist;
Remove all debris and spoils from the lot cleaning and tree pruning.
In locations where paving is to occur within the tree canopy, grub only
and do not grade nor compact. Install porous pavers over a three-inch
bed of ¾ inch granite covered with one-inch pea gravel for screeding. If
curbs are required, use pegged curbs to secure the porous pavers.
Pegged curbs are reinforced six to eight curbs poured at grade with a
one-foot by one-foot pothole every four to six linear feet.
All trenching or grading within the protected root zone area, outside of
the tree protection fence shall require hand trenching or preserve and
protect roots that are larger than 2 inches in diameter.
No grading or trenching is allowed within the fenced protected area.
Any roots that are 4 inches in diameter or larger are not to be cut until
inspected and approved by the on-site arborist.
(d) Upon project completion and prior to final occupancy a final status report
shall be prepared by the project arborist certifying that the tree protection
plan was implemented, the trees designated for protection were protected
during construction, and the construction-related tree protection measures
are no longer required for tree protection.
Mitigation Measure 4.e.2:
1. All existing trees outside of the limits of work shall remain.
2. Earthwork shall not exceed the limits of the project area.
3. Low branches in danger of being torn from trees shall be pruned prior
to any heavy equipment work being done.
4. Vehicles and stockpiled material shall be stored outside the drip line of all
trees.
5. All trees within twenty feet of construction work shall be fenced for
protection with 4-foot chain link, snow or safety fencing placed per the
approved tree protection plan. Tree protection fencing shall be in place
prior to any site excavation or grading. Fencing shall remain in place until
completion of all construction activities.
6. Any roots that are encountered during excavation shall be clean cut by
hand and sealed with an approved tree seal.
7. Utilities such as water, gas, power, cable, storm drainage, and sewer
should be redirected from under the canopy of any trees that are to remain.
8. Where a building is placed within the canopy of a tree the foundation
should be redesigned so that it bridges across any root systems.
9. Any foundation or other structure that encroaches within the drip line of
trees to be saved shall be dug by hand.
10. At no time shall tree roots be ripped with construction equipment.
BP BS/PS 4.e.2
Mitigation 5.d.1: Should any human remains be discovered on the property, all
work on the project should stop and the County Coroner contacted. If the
human remains are identified as being Native American, the California Native
American Heritage Commission (NAHC) should be contacted at (916) 653-
Ongoing PS 5.d.1
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
Conditions of Approval /
Mitigation Monitoring Program
Atascadero Avenue Triangle
9-Lot Planned Development 7
CUP 2007-0208/ZCH 2007-0145/TTM 2007-0101
Timing
GP: Grading Permit
BP: Building Permit
SIP: Subdivision
Improvement Plans
FM: Final Map
TO: Temporary
Occupancy
FI: Final inspection
FO: Final
Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
AMWC: Water Comp.
Mitigation
Measure
4082.
Mitigation Measure 6.b.1: All cut and fill slopes shall be hydro seeded with an
appropriate erosion control method (erosion control blanket, hydro-mulch, or
straw mulch appropriately anchored) immediately after completion of earthwork
between the months of October 15 through April 15. All hydroseed mix shall be
native species. All disturbed slopes shall have appropriate erosion control
methods in place. Duration of the project: The contractor will be responsible
for the clean-up of any mud or debris that is tracked onto public streets by
construction vehicles.
BP BS/PS 6.b.1
Mitigation Measure 8.e.f.1: The developer is responsible for ensuring that all
contractors are aware of all storm water quality measures and that such
measures are implemented. Failure to comply with the approved construction
Best Management Practices will result in the issuance of correction notices,
citations, or stop orders.
BP BS/PS 8.e.f.1
Mitigation Measure 11.d.1: All construction activities shall comply with the City
of Atascadero Noise Ordinance for hours of operation.
BP BS/PS 11.d.1
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT B: Master Plan of Development/Site Plan
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT C: Floor Plan A/B/C
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT D: Floor Plan A/B/C Elevations and Options
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT D: Floor Plan A/B/C Elevations and Options
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT E: Floor Plan D
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT F: Floor Plan D Elevations
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT F: Floor Plan D Elevations
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT G: Color Boards and Site Plan Color Key
TBD
TBD
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT G: Color Boards and Site Plan Color Key
Color Scheme #1 A “Clay Urn” to be substituted for a more muted color per
conditions of approval. Requires City Staff approval.
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT G: Color Boards and Site Plan Color Key
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT G: Color Boards and Site Plan Color Key
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT H: Preliminary Landscape Plan
See Following Page for Revised Plan
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT H: Preliminary Landscape Plan
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT I: Tree Protection Plan
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT J: Grading, Drainage and Utility Plans
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT J: Grading, Drainage and Utility Plans
t:\- 07 plns\pln 2007-1243 triangle park gpa - city\2014-pshh amendment\planning commission\pc resolution 2014-0027.docx
EXHIBIT K: Improvement Plans