EXHIBIT B: Conditions of Approval
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
Planning Conditions
1. The approval of this application shall become final, subject to the
completion of the conditions of approval, fourteen (14) days
following the Planning Commission approval unless prior to the
time, an appeal to the decision is filed as set forth in Section 9-
1.111(b) of the Zoning Ordinance.
On-going PS
2. This Conditional Use Permit shall be for a 26,500± square foot
commercial mixed-use retail development consisting of retail
space (10,000 sf); a sit down restaurant (5,000 sf) with an upstairs
bar/lounge (4,500 sf); and office space on the 2nd floor of buildings
(7,500 sf) on a 1.5± acre site with a freestanding freeway pole
sign.
BP PS
3. The existing cellular communication facility shall remain in place
subject to the conditions of CUP 2002-0062.
On-going PS
4. The Community Development Department shall have the authority
to approve the following minor changes to the project that (1)
modify the site plan project by less than 10%, and/or (2) result in a
superior site design or appearance.
BP PS
5. Approval of this Conditional Use Permit shall be valid for twenty-
four (24) months after its effective date. At the end of the period,
the approval shall expire and become null and void unless the
project has received a building permit or a time extension has
been granted.
BP PS
6. The applicant and/or subsequent owners shall defend, indemnify,
and hold harmless the City of Atascadero or its agents, officers,
and employees against any claim or action brought to challenge
an approval by the City, or any of its entities, concerning the
proposed development.
On going PS
7. The project shall provide a minimum of 70 off street parking
spaces within the project site, for project customers and
employees.
BP PS
8. Prior to the issuance of on-site construction permits, the
applicant shall record reciprocal public access easement on
driveways indicated on Exhibit C.
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
9. Prior to the issuance of on-site construction permits, the
applicant shall record a pedestrian access easement along the
southern side of the plaza feature in front of Building “A” along
El Camino Real consistent with Exhibit C. The historic “El
Camino Real” bell monument shall be relocated and
incorporated into the plaza.
BP PS
10. An exception to the height limitations of the Downtown
Commercial zoning district shall be allowed for all structures
within the development. Building heights shall not exceed 37-
feet in height consistent with Exhibit D.
BP PS
11. Architectural elevations, colors, materials, and signs shall be
shall be consistent with the character of the elevations shown on
Exhibit E.
BP PS
12. Final colors and exterior finishes shall be submitted to Staff for
review.
BP PS
13. The rear elevation of the building that is visible from US 101
shall include substantive architectural treatments and materials.
BP PS
14. All trash enclosures shall be constructed of masonry with solid
metal gates. The walls and gates shall be architecturally
coordinated with the project architecture.
BP PS
15. All roof top mechanical equipment shall be screen from view in
all directions.
BP PS
16. Final approval of site landscaping, irrigation, plant material,
streetscape, hardscape and site furniture shall be approved by
the Planning Staff and consistent with Exhibit E.
BP PS
17. Complete grading, drainage, utility, storm water management
plans with low impact development bio-swale features and
handicapped accessibility plans shall be submitted at time of
building permit.
BP PS
18. Prior to building permit issuance, a tree mitigation fee of $200
shall be paid for the removal of one 6-inch white oak tree.
BP PS
19. A freeway oriented pole sign shall be permitted on-site with the
maximum height determined by a balloon visibility test, the
Design Review Committee shall approve the height of the sign.
Pole sign shall have a decorative cap, and shall include the
City’s Logo and “Downtown Atascadero” on the face of the sign.
The City’s Logo and “Downtown Atascadero” shall not count
against the maximum signage area. The Design Review
Committee shall approve the maximum total signage area.
BP PS
20. The color of the freeway sign pole shall be a dark earthtone
consistent with the City’s Wayfinding Program and Exhibit F.
BP PS
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
GENERAL PUBLIC WORKS REQUIREMENTS
21. Applicant agrees to develop the site frontage and public
improvements in accordance with City Standard Engineering
Plans and Specifications.
22. Applicant shall file a Parcel Map to merge subject lots in
accordance with the Conditional Use Permit Site Plan.
23. Concurrent with Parcel Map approval, the applicant shall record
a reciprocal access easement and maintenance agreement for
all shared driveways and drive isles between Atascadero Mall
and the Jack-in-the-Box property, as directed by the City
Engineer.
24. Prior to Parcel Map approval, the applicant shall remove existing
structures.
25. Prior to Parcel Map approval applicant shall quitclaim or relocate
easements running through proposed structures, as directed by
the City Engineer.
26. At map check submittal, the applicant shall provide a preliminary
subdivision guarantee. A final subdivision guarantee is required
prior to Final Parcel Map approval. Prior to final parcel map
approval, the applicant is tentatively required to grant
easements on the final map (or if located outside the map
boundary, the applicant shall grant easements by means of
separate document). The easements shall be reviewed and
approved by the City Engineer.
27. Prior to recording the lot merger parcel map, the applicant shall
submit a copy of a valid tax bond. This may be waived by the
City Engineer if a tax bond is not required by the County of San
Luis Obispo for recording purposes.
28. All existing and proposed utility, pipeline, open space, or other
easements are to be shown on the lot merger map. If there are
building or other restrictions related to the easements, they shall
be noted on the parcel map. The applicant shall show all
access restrictions on the parcel map.
29. The applicant shall relocate all public and private utilities that
conflict with the proposed project. The applicant shall provide
easements for the relocated utilities if required by the owners.
30. Prior to final parcel map approval applicant shall submit Will
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
Serve Letters from all utility companies serving the project site.
Road Abandonment Requirements
31. Prior to issuance of building permits, the applicant shall obtain a
road abandonment for the portion of Atascadero Avenue
overlying 030-193-003. The applicant shall grant back to the
City a public access easement covering the portion of the lot
that will be used for public ingress and egress.
32. Prior to issuance of building permits, the applicant shall
extinguish 1) an easement (88-OR-114) for road purposes
recorded May 22, 1930, shown on Parcel Map CO-68-61, and 2)
a landscape easement granted to the City of Atascadero. The
applicant shall grant back to the City a public access easement
covering the portion of the road easement that will be used for
public ingress and egress.
33. Prior to issuance of building permits, the applicant shall file for
and obtain a lot merger for all parcels affected by the project.
Bonds, Fees and Miscellaneous Requirements
34. Prior to issuance of encroachment permits for public
improvements (street, sewer, storm drain, water), the applicant,
by improvement agreement with the City Engineer, shall
guarantee installation of the improvements through faithful
performance bonds, letters of credit or any other acceptable
means. Building final shall be withheld if the improvements are
not completed.
Grading and Drainage
35. Prior to storm drain plan approval, the applicant shall grant all
easements needed for future maintenance of public storm drain
facilities by the City.
36. Prior to grading permit, the applicant shall obtain approval of a
drainage study for the proposed private onsite and public offsite
storm drain system from the City Engineer. The study shall
demonstrate that runoff generated onsite will not negatively
affect downstream waterways or properties. Onsite retention
and detention basins, including bioswales shall be employed to
the satisfaction of the City Engineer. Offsite storm drain
facilities needed for compliance with City Engineering Standards
identified in the drainage study shall be installed.
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
37. Prior to issuance of grading permits affecting Caltrans right-of-
way, the applicant shall submit written approval from Caltrans
for the proposed construction within Caltrans right-of- way.
38. Maintenance responsibilities for all drainage devices, and
erosion and sedimentation control devices/systems not
transferable to the City shall be the responsibility of the property
owner.
39. Prior to grading permit, the applicant shall obtain a notarized
Letter of Permission for grading over all easements.
40. Applicant shall submit erosion control plans and a Storm Water
Pollution Prevention Plan (if the area of disturbance is greater
than an acre.
41. The applicant or subsequent property owners shall also be
responsible for providing regularly scheduled maintenance of
the storm drain infrastructure, as directed by the City Engineer.
42. Prior to Parcel Map approval, the applicant shall place a note on
the map, prohibiting the lot owners within this development from
interfering with the established drainage master plan and from
erecting walls, curbs or similar solid constructions, exce pt as
approved by the City Engineer.
Street Improvement Requirements
43. Applicant shall install Downtown Streetscape Standard curbs,
gutters and sidewalks including decorative lights and street
trees along the project frontage on El Camino Real and
Atascadero Mall in accordance with City Standards. The
irrigation system shall be tied into existing City facilities,
including controllers and distribution laterals.
44. The proposed signalization of the intersection of the main
access driveway into the La Plaza site and El Camino Real,
including loop detectors, shall be constructed in accordance with
City Engineering Standards, and approved by the City Engineer.
45. The intersection of the driveways with El Camino Real shall be
modified as necessary to meet site distance, horizontal and
vertical alignment standards of the City Engineering Standards.
46. All pedestrian facilities shall comply with the applicable
requirements of the Americans with Disabilities Act.
47. Prior to any construction (including, but not limited to, drive
approaches, sidewalks, curbs and gutters, etc.), trenching or
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
grading within public or private street right-of-way, the applicant
shall submit a street improvement plan consistent with the
adopted Downtown Streetscape Standards and the conditions of
approval and obtain encroachment permits from the City
Engineer.
48. Applicant shall submit a composite utility plan, signed by PG&E,
AT&T, Charter Cable TV and Southern California Gas Company
indicating location of all underground utilities within the public
right-of-way to serve the project. Plan shall be reviewed and
approved by the City Engineer prior to approval of public
improvement plans.
49. Prior to building final, all new and existing power lines and
overhead cables less than 34 KV within or fronting the project
site shall be installed underground.
50. Prior to Parcel Map approval, the applicant shall dedicate
sidewalk easements sufficient to encompass ADA requirements
for sidewalks installed with drive approaches in accordance with
the current City standard, or equivalent.
51. Prior to building final, the applicant shall construct full street
improvements to the satisfaction of the City Engineer.
52. Prior to Parcel Map approval, the applicant shall pay fees for
signing and striping of streets as determined by the City
Engineer or shall prepare signing and striping plans for El
Camino Real, as directed by the City Engineer.
53. Prior to building final, the applicant shall install mailboxes and
posts in accordance with the City’s standards, and secure
approval of the U.S. Postal Service prior to installation.
54. Prior to building final, the applicant shall construct wheelchair
ramps at intersections, as directed by the City Engineer.
Sewer Improvement Requirements
55. Applicant shall pay sewer extension (Annexation), Connection
and Reimbursement fees (if applicable) upon issuance of
building permit.
56. The existing sewer main in Atascadero Mall shall be relocated
as necessary to avoid proposed improvements. Relocated main
shall be located within a 20-foot wide sewer easement to be
dedicated by applicant as directed by City Engineer.
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
57. Prior to issuance of building permits for each component of the
Conditional Use Permit, the project applicant shall submit plans
to the City for approval that demonstrates compliance with the
City Sanitary Sewer Management Plan, including City standards
for the Fats, Oils and Grease (FOG) Program; and the
installation of adequately sized grease interceptors for all food
service establishments (FSEs).
58. The sewer plans shall be reviewed and approved by the City
Engineer.
59. Existing sewer manhole frame and covers relocated or adjusted
due to street or other construction shall be replaced with current
City Standard Manhole Cover per City Engineering Standards.
60. Prior to issuance of building permits, the applicant shall
construct separate laterals to serve each building.
61. The main-line sewers located in the public/private streets shall
be a publicly maintained. All other sewer lines shall be privately
maintained.
Traffic
62. The project applicant shall implement the following traffic
mitigation measures.
a. Prior to issuance of the final certificate of occupancy for the
project, the intersection of El Camino Real/West Mall
Avenue/ Main Driveway shall be improved with modified
signals and equipment as needed by the project applicant.
b. The project applicant shall revise the improvement plans to
provide for a northbound left-turn lane on El Camino Real at
the new main driveway serving the site. The City Engineer
shall review and approve the lane geometry.
c. Prior to issuance of the final certificate of occupancy for the
project, the applicant shall install bicycle facilities (racks) in
convenient locations. Bicycle storage shall be provided at a
ratio of no less than 1 bicycle space for each 20 vehicular
spaces.
d. Prior to acceptance of improvements to El Camino Real the
project frontage improvements on El Camino Real shall
include Class II bicycle lanes as a component of the signal
installation at El Camino Real.
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
City Council Conditions
63. All project driveways shall be marked as no parking areas with
red curbing.
FO PW
64. The applicant will make a good faith effort to assist in the
relocation of the Malibu Brew business during construction.
BP CD
TEMPORARY INDOOR RECREATIONAL USES CONDITIONS
63. Indoor Recreational uses are allowed within the master plan of
development in the area consistent with Exhibit G.
BP PS
64. Indoor Recreational uses must be contained in a temporary tent
structure or other similar structure totaling no more than 10,800
square feet.
BP / FI PS
65. Applicant must apply for building permits to allow for the
temporary tent structure, wood flooring, and all on-site work
including any structure greater than 120 square feet.
BP BS
66. Applicant must meet all accessibility requirements and exiting
requirement for health, safety, and welfare of users of the indoor
recreational uses consistent with the California Building Code.
BP / FO PS / BS / FD
67. Applicant may not commence construction prior to issuance of a
building permit.
BP PS
68. Applicant may not occupy the structure nor be open for public
use prior to issuance of final occupancy with inspections by the
Planning Department, Fire Marshall, and Chief Building
Inspector.
FO PS / BS / FD
69. Indoor Recreational uses may include the following:
Ice Skating
Roller Skating
Indoor Soccer
Other indoor recreational type uses that can be
contained within the temporary tent structure
FO PS
70. Additional ancillary uses to the indoor recreational uses may be
allowed as shown in Exhibit G. Additional ancillary uses will
require an amendment to the master plan of development.
BP PS
71. A temporary caretaker’s residence is permitted in the area
shown in Exhibit G. Caretaker’s residence must pump effluent
from the trailer that does not cause a health and welfare
BP PS
Exhibit B
Conditions of Approval / Mitigation Monitoring Program
PLN 2013-1466 / CUP 2013-0268 6322 through 6500 El
Camino Real (La Plaza)
Timing
GP: Grading Permit
BP: Building Permit
TO: Temporary Occupancy
FI: Final inspection
FO: Final Occupancy
Responsibility
/Monitoring
PS: Planning Services
BS: Building Services
FD: Fire Department
PD: Police Department
CE: City Engineer
WW: Wastewater
CA: City Attorney
Mitigation
Measure
nuisance.
72. A minimum fire clearance of 20-feet is required at the rear of the
property. Fire clearance must be approved by the Fire Marshall
prior to occupancy and include removal of all construction
related material, and any additional debris. Fire Clearance must
be maintained for the duration of the temporary indoor
recreation use.
FO FD/BS
73. Special Events such as roller derby, indoor recreational
tournaments, etc. are allowed on-site once (1) every thirty (30)
days. This is effective as of the date of final occup ancy
issuance.
FO PS
74. Live Concerts / DJ Music and other amplified noise sources are
permitted on-site. Amplified music is permitted to play until 10
p.m. and limited to one (1) occurrence a week. A week is
defined as business operations Sunday through Sa turday. Any
additional amplified music may be used but shall be consistent
with the City’s Noise Ordnance.
FO PS
75. Indoor recreational uses are temporary. Indoor recreational uses
shall cease operation no later than March 30, 2015.
FO PS
76. Applicant will have 30 days prior to or on April 1, 2015 to return
the site to its previous condition.
FO PS
EXHIBIT C: Proposed Site Plan
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
Provide
pedestrian
easement at
the end of
median
property
Relocate
and
incorporate
El Camino
Real Bell
into plaza.
Provide public
access
easements on
driveways
Existing cellular
communication
facility to remain
Median property
to remain City
owned. Proposed
improvements
and building
demolition to be
permitted with
frontage
improvement
encroachment
permit.
EXHIBIT D: Proposed Architecture Elevations
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
EXHIBIT D: Proposed Architecture Elevations
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
EXHIBIT D: Proposed Architecture Elevations
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
EXHIBIT D: Proposed Architecture Elevations
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
EXHIBIT E: Proposed Landscape Plans
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
Pole Sign Location
EXHIBIT F: Proposed Freeway Oriented Signage
PLN 2013-1466 / CUP 2013-0268
6322 through 6500 El Camino Real (La Plaza)
Sign to include
“Downtown
Atascadero” and City
Logo (excluded from
total signage area and
height restriction)
DRC to approve
maximum sign size
DRC to
approve
final sign
height
EXHIBIT G: Site Plan – Temporary Indoor Recreational Use
PLN 2013-1466 / CUP 2013-0268 – Amendment
6322 through 6500 El Camino Real (La Plaza)
Indoor Recreational Uses shall cease operation on or before March 30, 2015
EXHIBIT G: Fire Clearance
PLN 2013-1466 / CUP 2013-0268 – Amendment
6322 through 6500 El Camino Real (La Plaza)
Fences and other debris and construction related materials shall be removed and
provide a minimum 20-foot Fire clearance prior to Final Occupancy and must be
maintained at all times.