Staff Report - Administrative Services
ITEM NUMBER: C - 1
DATE: 10/26/10
Historic City Hall Project Bid Awards:
ACH-03 Basement Wall & Floor Demolition, and
ACH-04 Basement Electrical Demolition
and Temporary Power Installation
RECOMMENDATIONS:
Council:
1. Award bid to, and authorize the City Manager to execute a contract with, Allied
Industries in the amount of $178,000.00 for the ACH-03 Basement Wall and
Floor Demolition services for the Historic City Hall Project; and,
2. Award bid to, and authorize the City Manager to execute a contract with, Rossi
and Carr in the amount of $73,977.57 for the ACH-04 Basement Electrical
Demolition and Temporary Power Installation services for the Historic City Hall
Project.
DISCUSSION:
The first two bids for the Historic City Hall Project are ready to award and came in well
below the expected budget. These two bids will be followed by others, as the City will
hold multiple contracts using the multi -prime approach to construction management.
The Historic City Hall Project is a large project. The demolition of the basement is the
first step in restoring the building. The demolition will reveal additional information on
the existing foundation and is expected to reduce the number of unknowns for future
bids.
ACH-03 Basement Wall & Floor Demolition
ACH-03 Basement Wall & Floor Demolition was released for bidding on September 1,
2010. The bid was posted on the City's web site, in the Atascadero News, in plan
rooms across California, and one large plan room in Georgia. The bid package
ITEM NUMBER: C - 1
DATE: 10/26/10
includes the complete demolition and removal of the basement floor and non-bearing
continuous masonry unit walls and unreinforced hollow clay block walls. In addition,
included in this scope, are some exploratory excavations around and adjacent to some
existing foundations. There is also a minor amount of site demolition included in this
scope.
Twelve contractors attended the mandatory pre-bid walk-through of the project site,
many of whom were locally -based. Out of those twelve, five bids were received.
Allied Industries out of North Hollywood, California, was the lowest responsive bidder
with a bid of $178,000. The bid came in well under both the budgeted amount for this
package and other bidders. Because there was a large range in the bids,
representatives from Bernards contacted Allied Industries and were assured that they
understood the scope of work and that they stand by their bid.
Contractor
Package budget
Package bid
Allied Industries
$ 379,750.00
$178,000.00
The majority of this portion of the rehabilitation will fall under the "FEMA Mitigation"
category of work.
ACH-04 Basement Electrical Demolition & Temporary Power Installation
ACH-04 Basement Electrical Demolition & Temporary Power Installation was also
released for bidding on September 1, 2010. Like ACH-03, the bid package for ACH-04
was posted on the City's web site, in the Atascadero News, in plan rooms across
California, and one large plan room in Georgia. The bid package includes the
demolition, removal, labeling and storage of all electrical panels in the Basement. In
addition, all switches and power outlets are to be removed in preparation for
demolition. A new 400 amp temporary power supply and lighting system is to be
installed to service the building with power and lighting for the duration of the project.
Eleven contractors attended the mandatory pre-bid walk-through of the project site.
Many of those contractors were locally -based. Out of those eleven, four bids were
received. Rossi and Carr, out of Paso Robles, was the lowest responsive bidder.
The bid came in well under the budgeted amount for this package. The budget was set
at $162,750 and the bid from Rossi & Carr came in at $73,977.57
Contractor
Package budget
Package bid
Rossi & Carr
$ 162,750
$ 73,977.57
The majority of this portion of the rehabilitation will fall under the "FEMA Mitigation"
category of work.
ITEM NUMBER: C - 1
DATE: 10/26/10
Requests for Qualifications (RFQ) on bid package ACH-01 Deputy Inspection Services
were received on October 15, 2010. Updates to Council will be forthcoming as
progress continues on the selection of qualified Deputy Inspection Services.
FISCAL IMPACT:
PROJECTED FUNDING USES'
Architecture and engineering
$ 5,030,000
Construction costs:
6,686,400
ACH-3 Basement Wall and Floor Demolition $ 178,000
2,000,000
ACH-4 Basement Electrical Demolition and
Temporary Power Installation 73,980
13,000,000
Remaining bid packages 24,619,020
$ 41,745,590
Total construction costs
24,871,000
Construction management
3,231,010
General conditions, construction support, and
permitting
1,519,420
Contingency (20%)
5,032,300
TOTAL PROJECTED FUNDING USES
$ 39,683,730
PROJECTED FUNDING SOURCES
Expected FEMA funding $
20,059,190
Expected Cal E MA funding
6,686,400
California Cultural Historic Endowment Grant
2,000,000
Redevelopment 2010 Bond Funds
13,000,000
TOTAL PROJECTED FUNDING SOURCES
$ 41,745,590
FUNDING SURPLUS $ 2,061,860
The Project cost summary as presented to Council on July 27, 2010 estimated
construction costs at $25,161,524 and a total project cost of $39,974,254. While there
are still many more bids to come, the table above shows current projections to be about
$290,520 lower than the July 2010 projections and about $2,061,860 lower than the
current Project budget.
ATTACHMENTS:
Exhibit A —ACH-03 Bid Summary
Exhibit B — ACH-04 Bid Summary
Exhibit A
Bid Summary
TO: Public Works
FROM: Lisa Cava, Deputy City Clerk f
BID NUMBER: 2010-003
BID DESCRIPTION: City Hall Basement Electrical
BID OPENING: 10-14-10 @ 2:00 pm
Total Base Bid
Vendor Amount A-1 Bid Alternate B-1 Bid Alternate B-2 add/deduct
Rossi & Carr
Black Dog Electric
73,977.57
63,700.00
21182,20
1,406.00
21,611.18
6,000.00
Advanced Electric
Brannon, Inc
124,730.00
145,41100
240.00
1,62540
6,200,00
5,000,00
I
City of Atascadero
iffice of the City Clerk
Exhibit B
add/deduct
ADD
Bid Summary
TO:
Public Works
FROM:
Lisa Cava, Deputy City Clerk
BID NUMBER:
2010-004
BID DESCRIPTION:
City Hall Basement Wall & Floor Demo
BID OPENING:
10-14-10 @ 2:30 pm
Total Base Bid
Vendor
Amount A-1 Bid Alternate B-1 Bid Alternate B-2
Allied Industries
178,000.00 6,000.00
12,0()0.00
Central Coast Casualty Restoration
296,919.00 4,500.00
30,000-00
Channel :oast
319,500.00 21717-00
1,913.00
The Main Company, dba
332,500.00 400.00
5,000.00
Miller Environmental
341,000.00 14,000X0
- I
9'900.00
I
Exhibit B
add/deduct
ADD