HomeMy WebLinkAboutResolution 2005-077 RESOLUTION NO. 2005-077
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF ATASCADERO, CALIFORNIA, APPROVING
VESTING TENTATIVE TRACT MAP 2005-0067, A SIXTY-TWO LOT
SUBDIVISION CONSISTENT WITH A MASTER PLAN OF
DEVELOPMENT ON APN 049.042-018
(1155 El Camino Real / Wehn Group LLC)
WHEREAS, an application has been received from Wehn Group LLC (934 Sycamore
Canyon, Paso Robles, CA 934461 Applicant and Property Owner, to consider a project const sting
of a Zone Change from RMF-16 (Residential Multi-family-16) to RMP-16/ PD26 (Residential
Multi-Family-16 with a Planned Development Overlay 26) with conesponding Master Plan of
Development and Vesting Tentative Tract Map on a 5.47-acre site located at 1155 El Camino
Real,(APN 049-042-018); and,
WHEREAS, the site's General Plan Designation is HDR (High Density Residential);
and,
WHEREAS, the Planning Commission has recommended that the site's Zoning District
be changed from RMF-16 (Residential Multi-Farm))-16) to RMF-16/PD 26 (Residential Moln-
Family-16/Planned Development Overlay 26): and,
`%W
WHEREAS, an Initial Study and Draft Mitigated Negative Declaration 2005-0028 were
prepared Cor the project and made available for public review in accordance with the
requirements of the Califomia Environmental Quality Act (('EQA); and,
WHEREAS, the laws and regulations relating to the preparation and public notice of
environmental documents, as set forth in the State and local guidelines for implementation of the
California Environmental Quality Act (CEQA) have been adhered to; and,
WHEREAS, a timely and properly noticed Public Hearing upon the subject Vesting
Tentative Tract Map application was held by the Planning Commission of the City of Atascadero
at which hearing evidence, oral and documentary, was admitted on behalf of said Master Plan of
Development: and,
WHEREAS, the Planning Commission of the City of Atascadero, at a duly noticed
Public Hearing held on July 19, 2005 studied and considered Tentative Tract Map 2005-0067,
after first studying and considering the Proposed Mitigated Negative Deelar ation prepared for the
project, and
WHEREAS, the City Council of the City of Atascadero, at a duly noticed Public Hearing
held on August 9, 2005, studied and considered Tentative Tract Map 2004-0067, after first
studying and considering the Proposed Mitigated Negative Declaration prepared for the project;
1tr and,
City of Ataseadero
Resolution No.2005-077
Page 2 of 17
r NOW THEREFORE, the City Council of the City of Atascadero takes the following
actions:
SECTION 1. Findings of Approval for Vesting Tentative Tract Map, the City
Council finds as follows:
1. The proposed subdivision, design and improvements as conditioned, is consistent with
the General Plan and applicable zoning requirements, including provisions of the PD-26
overlay district.
2. The proposed subdivision, as conditioned, is consistent with the proposed Planned
Development Overlay District-26 Master Plan of Development (CUP 2005-0167).
3. The site is physically suitable for the type of development proposed.
4. The site is physically suitable for the density of development proposed.
5. The design and improvement of the proposed subdivision will not cause substantial
environmental damage or substantially and unavoidably injure fish and wildlife or their
habitat.
6. The design of the subdivision will not conflict with easements acquired by the public at
large for access through, or the use of property within, the proposed subdivision; or
substantially equivalent alternative easements are provided.
7. Covenants, Conditions and Restrictions (CC&R's) or equivalent shall be required that
incorporate the Master Plan of Development conditions of approval to ensure that the site
retains the proposed qualities (architecture, colors, materials, plan amenities, fencing, and
landscaping) over time.
8. The proposed subdivision design and type of improvements proposed will not be
detrimental to the health, safety or welfare of the general public.
City of Atascadero
Resolution No.2005-077
Page 3 of 17
SECTION 2. Approval. The City Council of the City of Atascadero, in a regular
session assembled on August 9, 2005, resolved to approve Vesting Tentative Tract Map (TTM
2005-0067) subject to the following:
1. Exhibit A: Vesting Tentative Tract Map 2005-0067
2. Exhibit B: Conditions of Approval /Mitigation Monitoring Program.
On motion by Council Member O'Malley and seconded by Council Member Pacas, the
foregoing Resolution is hereby adopted in its entirety on the following roll call vote:
AYES: Council Members O'Malley, Pacas and Mayor Scalise
NOES: None
ABSENT: Council Members Clay and Luna
ADOPTED: August 9, 2005
CITY OF ATASCERO
By:
W dy S�Z� ise, Mayor
ATTEST:
L
Marcia McClure Torgerson, C.M.C., ity Clerk
APPROVED AS TO,FORM:
Patrick.Enrig ty ity Attorney
°err
City ofstascadero
.2005-01
gesolutiou NO
Page A of 1� root Map
Tentative T
1EXh'pit A:Ve$tin9
l
,
,
3
`v-s•'' 1 A
City of Ataseadero
Resolution No.2005-077
Page 5 of 17
Exhibit B:Conditions of Approval/Mitigation Monitoring Program
�Irw Tentative Tract Map 2005-0067
Conditions of Approval/ Timing Responsibility Mitigation
Mitigation Monitoring Program /Monitoring Measure
GP:Grading Permit PS:Planning Services
BP:Building Permf BS.Building Services
The Village at Oakhaven SIP:Subdivision FD:FireDepartmant
Vesting Tentative Tract Ma Improvement Plans PD:Police Engineer ent
9 p FM:Final Map CE.City Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA:City Attorney
Fl:Final inspection AMWC:Water Carp.
F0:Final Occupancy
Planning Services
1. The approval of this use permit shall become final and effective for the FM PS
purposes of issuing building permits thirty(30)days following the City
Council approval of ZCH 2005-0099 and ZCH 2005-0101 upon second
reading,unless prior to that time,an appeal to the decision is filed as set
forth in Section 9-1.111(b)of the Zoning Ordinance.
2. Approval of this Tentative Tract Map shall be valid for two years after its FM PS
effective date. At the end of the period, the approval shall expire and
become null and void unless an extension of time is granted pursuant to a
written request received prior to the expiration date.
3. The Community Development Department shall have the authority to FM PS
approve minor changes to the project that (1) result in a superior site
design or appearance, and/or (2) address a design issue that is not
substantive to the Tentative Tract Map and that the Final Map is in
substantial conformance with the Tentative Map.
4. The granting of this entitlement shall apply to the property located at(APN on going PS
049-042-018) regardless of owner.
5. The Final Map shall be drawn in substantial conformance with the FM PS
approved tentative map, and in compliance with all conditions set forth
herein,shall be submitted for review and approval in accordance with the
Subdivision Map Act and the City's Subdivision Ordinance.
6. The subdivider shall defend, indemnify, and hold harmless the City of FM PS
Atascadero or its agents, officers, and employees against any claim or
action brought to challenge an approval by the city, or any of its entities,
concerning the subdivision.
7. The Tract Map shall be subject to additional fees for park or recreation FM PS
purposes(QUIMBY Act)as required by City Ordinance.
8. The emergency services and facility maintenance costs listed below BP PS
shall be 100%funded by the project in perpetuity. The service and
maintenance costs shall be funded through a community facilities
district established by the City at the developer's cost. The funding
mechanism must be in place prior to or concurrently with acceptance of
the final maps. The funding mechanism shall be approved by the City
Attorney,City Engineer and Administrative Services Director prior to
acceptance of any final map. The administration of the above
mentioned funds shall be by the City. Developer agrees to participate
�41111iw in the community facilities district and to take all steps reasonably
City of Atascadero
Resolution No.2005-077
Page 6 of 17
Conditions of Approval I Timing Responsibility Mitigation
'%W Mitigation Monitoring Program /Monitoring Measure
GP:Grading Permit PS:Planning Services
BP:Building Permit BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:Fire Department
Improvement Plans PD:Police Department
Vesting Tentative Tract Map FM:Final Map CE:City Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA City Anomey
FI:Final inspeclion AMWC:Water Comp.
F0:Final Occupancy
required by the City with regard to the establishment of the district and
assessment of the property.
• All Atascadero Police Department service costs to the project.
■ All Atascadero Fire Department service costs to the project.
■ Off-site common City of Atascadero park facilities maintenance
service costs related to the project.
9. All tract maintenance costs listed below shall be 100% funded by the BP PS
project in perpetuity. The service and maintenance cost shall be funded
through a Home Owners Association established by the developer subject
to City approval. The Horne Owners Association must be in place prior to,
or concurrently with acceptance of any final maps. The Home Owners
Association shall be approved by the City Attorney, City Engineer and
Administrative Services Director prior to acceptance of any Final Map.
The administration of the above mentioned funds, and the coordination
and performance of maintenance activities, shall be the responsibility of
the Home Owners Association.
All streets, bridges, sidewalks, streetlights, street signs, roads,
emergency access roads, emergency access gates, and sewer
mains within the project.
■ All parks,traits, recreational facilities and like facilities.
■ All open space and native tree preservation areas.
■ All drainage facilities and detention basins.
■ All creeks, flood plains, floodways, wetlands, and riparian
habitat areas.
• All common landscaping areas, street trees, medians,
parkway planters, manufactured slopes outside private yards,
and other similar facilities.
• All frontage landscaping and sidewalks along arterial streets
10. Prior to final map, the applicant shall submit CC&Rs for review and BP PS
approval by the Community Development Department. The CC&R's shall
record with the Final Map and shall include the following:
a) Provisions for maintenance of all common areas including
access, parking, street trees, fencing and landscaping in
perpetuity.
b) A detailed list of each individual homeowner's responsibilities for
maintenance of the individual units.
14ilr'
City of Ataseadero
Resolution No.2005-077
Page 7 of 17
Conditions of Approval 1 Timing Responsibility Mitigation
Mitigation Monitoring Program /Monitoring Measure
GPGrading Permit PS:Planning Services
BP:Building Penni! BS:Building Services
The Village at Oakhaven SIP:Subdivisbn FD:Fire Department
VestingImproTentative Tract Ma FM:Fi al Mapenl Plans CECityEngleolice dment
P FM:Final Map CE:City Engineer
TTM 2005-0067 TO:Temporary WW:Waslewaler
Occupancy CA City Attorney
FI:Final inspection AMWC:Water Comp.
FO Final Occupancy
c) Residents shall keep all trash receptacles within the unit's
designated trash storage area.
d) Garages shall be maintained and used for vehicle parking.
e) No boats, RV's or other type of recreation vehicle may occupy a
guest or resident parking space, including within an individual
garage.
f) A provision for review and approval by the City Community
Development Department for any changes to the CC&R's that
relate to the above requirements prior to the changes being
recorded or taking effect.
11. Affordable Housing Requirement: The applicant shall deed restrict a GP/BP PS,CA
minimum of 12 residential units for 30 years,at the moderate income rate:
All units shall be distributed throughout the project,subject to staff
approval.
12. Workforce Housing: Prior to recordation of final map,the applicant shall BP PS,CA
enter into a legal agreement with the City to reserve 1/2 of the units for sale
to residents or workers within the City of Atascadero,including the
affordable units. The agreement shall include the following provisions:
■ The units shall be offered for sale to residents or workers within the
City of Atascadero for a minimum of 60-days. During this time period
offers may only be accepted from Atascadero residents or workers;
■ The applicant shall provide reasonable proof to the City that at least
one of the qualified buyers is a resident or worker within the City
Limits of Atascadero;
• The Atascadero resident or worker restriction shall apply to the initial
sale only;
■ The applicant shall identify which units will be reserved;and
The City Attorney shall approve the final form of the agreement.
13. The developer and/or subsequent owner shall assume responsibility for Ongoing PS
the continued maintenance of all landscape and common areas.
14. Deed notification shall be recorded against lots 24,25,and 26 expressing
the requirements and maintenance responsibilities of the landscape
buffer.
City Engineer Conditions
PROJECT SPECIFIC CONDITIONS
,%W
City of Ataseadero
Resolution No.2005-077
Page 8 of 17
Conditions of Approval/ Timing Responsibility Mitigation
1%W Mitigation Monitoring Program /Monitoring Measure
OR Grading Permit PS:Planning Services
BP:Building Permit BS:Building Services
The Village at Oakhaven SIP Subdivision FD:Fire Department
VestingImpravernent Tentative Tract Ma FM:Final
CE.CitPoly Engineer p FM:Final Map CE.Ciry Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA:CIIyAttorney
FI:Final inspection AMWC:Water Cone.
F0:Final Occupancy
Drainage:
1. Obtain approval by the City Engineer of the grading & drainage plan and BP,GP CE
the storm drain design&facilities.
2. Submit calculations to support the design of any structures or pipes. BP,GP CE
Closed conduits shall be designed to convey the 10-year flow with gravity
flow, the 25-year flow with head, and provide safe conveyance for the
100 year overflow.
3. Provide for the detention of the 50 year developed storm runoff, while BP,GP CE^
metering out the 2 year undeveloped storm runoff. Metered runoff must
follow existing drainage patterns.
4. Show the method of dispersal at all pipe outlets. Include specifications for BP,GP CE
size &type. Drainage calculations must show where water flows offsite,
and analyze downstream facilities to ensure adequate capacity.
5. Acquire drainage easements where needed. Drainage shall cross lot BP,GP CE
lines only where a drainage easement has been provided.
6. Concentrated drainage from off-site areas shall be conveyed across the BP,GP CE
project site in drainage easements. Acquire drainage easements where
needed. Drainage shall cross lot lines only where a drainage easement
has been provided. If drainage easement can not be obtained the storm
water release must follow the exact historic path, rate and velocity as
prior to the subdivision.
Public Improvements and Maintenance:
7. The applicant must provide for the repair and maintenance of on-site FM CE
shared improvements.This includes roads,sidewalks,street trees,
streetlights,private sewer system,drainage facilities, recreation areas
and common landscaping.The two methods that may be used are:
a. Homeowners Association.This private organization would be
responsible for the maintenance,repair and replacement of the facilities.
b.Assessment District and Landscape and Lighting District. Funds for the
maintenance,repair and replacement of the facilities would be collected
on the property tax bill and distributed to the City.
The City Engineer and City Attorney shall approve the final form prior to
recordation.
8. All public improvements shall be constructed in conformance with the City BP,GP CE
of Atascadero Engineering Department Standard Specifications and
Drawings or as directed by the City Engineer.
City of Atascadero
Resolution No.2005-077
Page 9 of 17
Conditions of Approval l Timing Responsibility Mitigation
Mitigation Monitoring Program
(Monitoring Measure
GP:Grading Permit PS:Planning Services
BP:Building Permit BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:Fire Department
VestinglaptoTentative Tract Ma FM:Fi al Mapent Plans PD:CityE Police EngDelpineer h FM:Final Map CE.City Engineer
TTM 2005-0067 TO:Temporary WW:Waslewater
Occupancy CA City Attorney
FI:Final inspection AMWC:Water Comp.
F0:Final Occupancy
9. The grade lines for all improvernents shown on the tentative map may be BP,GP CE
subject to change or adjustment by the City Engineer
10. Construction plans shall include plan and profile of sanitary sewer, storm BP,GP CE
drain lines,and waterlines.
11. Full frontage improvements are required with this development. These BP,GP CE
include curb, gutter, sidewalk and paveout. Public Improvement plans
shall be submitted detailing the design. Final alignment and
configuration of EI Camino Real shall be determined by the City
Engineer. This may require reconfiguration of roadway to allow for
parking and bicycle lanes.
12. All handicap ramps shall be constructed to current ADA requirements, BP, GP CE
including the use of truncated domes.
13. Prior to issuance of building permits,the applicant shall submit a grading BP,GP CE
and drainage plan with a separate sheet(s) devoted to sedimentation
and erosion control, prepared by a registered civil engineer for review
and approval by the City Engineer.
SANITARY SEWER CONDITIONS
14. The Public Works Department shall approve all wastewater facilities prior BP,GP CE
to construction. This includes pumps, force mains, cleanouts, manholes
and connections.
15. Applicant shall pay sewer extension (annexation) fees upon issuance of BP,GP CE
building permit. Sewer Connection and Reimbursement fees shall be
payable upon actual connection of the building sewer to the public sewer
system.
16. Gravity mains and other sewer facilities within the subdivision shall be BP,GP CE
privately owned and maintained.
17. Gravity mains within the subdivision shall be eight(8)inches in diameter. BP,GP CE
18. Gravity mains onsite shall end in a manhole. BP,GP CE
STANDARD CONDITIONS
19. All public improvements shall be constructed in conformance with the City BP,GP CE
of Atascadero Engineering Department Standard Specifications and
Drawings or as directed by the City Engineer.
20. In the event that the applicant is allowed to bond for the public FM CE
improvements required as a condition of this snap, the applicant shall
City of Atascadero
Resolution No.2005-077
Page 10 of 17
Conditions of Approval/ Timing Responsibility Mitigation
Vrr Mitigation Monitoring Program /Monitoring Measure
GP:Grading Permit PS:Planning Services
BP:Building Permit BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:Fire Department
Improvement Plans PD:Police Deparlment
Vesting Tentative Tract Map FM:Final Map CE.City Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA:City Allorney
FI:Final inspection AMWC:Water Comp.
F0:Final Occupancy
enter into a Subdivision Improvement Agreement with the City Council.
21. An engineer's estimate of probable cost shall be submitted for review and FM CE
approval by the City Engineer to determine the amount of the bond.
22. The Subdivision Improvement Agreement shall record concurrently with FM CE
the Final Map.
23. The applicant shall be responsible for the relocation and/or alteration of BP,GP CE
existing utilities.
24. The applicant shall install all new utilities (water, gas, electric, cable TV BP, GP GE
and telephone) underground. Utilities shall be extended to the property
line frontage of each lot or its public utility easement.
25. The applicant shall monument all property corners for construction control FM CE
and shall promptly replace them if disturbed.
26. The applicant shall acquire title interest in any off-site land that may be FM CE
required to allow for the construction of the improvements.The applicant
shall bear all costs associated with the necessary acquisitions. The
applicant shall also gain concurrence frorn all adjacent property owners
whose ingress and egress is affected by these improvements.
27. Slope easements shall be provided as needed to accommodate cut of fill FM CE
slopes.
28. Drainage easements shall be provided as needed to accommodate both FM CE
public and private drainage facilities.
29. The final map shall be signed by the City Engineer prior to the map being FM CE
placed on the agenda for City Council acceptance.
30. Prior to recording the tract map, the applicant shall submit a reap drawn FM CE
in substantial conformance with the approved tentative map and in
compliance with all conditions set forth herein. The map shall be
submitted for review and approval by the City in accordance with the
Subdivision Map Act and the City's Subdivision Ordinance.
31. Prior to recording the tract map,the applicant shall set monuments at all FM CE
new property corners. A registered civil engineer or licensed land
surveyor shall indicate by certificate on the parcel map, that corners have
been set or shall be set by a date specific and that they will be sufficient
to enable the survey to be retraced.
32. Prior to recording the map,the applicant shall complete all improvements FM CE
required by these conditions of approval
err'
City of Atascadero
Resolution No.2005-077
Page 11 of 17
Conditions of Approval/ Timing Responsibility Mitigation
Mitigation Monitoring Program /Monitoring Measure
GP:Grading Penmd PS:Planning Services
BP:Building Pernrl BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:FireDeparlmeni
Improvement Plans PD:Police Depadmenl
Vesting Tentative Tract Map FM:Final Map CE:Cry Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA:City Attorney
FI:Final inspection AMWC:Water Comp.
F0:Final Occupancy
33. Prior to recording the tract map, the applicant shall have the map FM CE
reviewed by all applicable public and private utility companies (cable,
telephone, gas, electric, Atascadero Mutual Water Company). The
applicant shall obtain a letter from each utility company indicating their
review of the map. The letter shall identify any new easernents that may
be required by the utility company. A copy of the letter shall be submitted
to the City. New easements shall be shown on the map.
34. Upon recording the final map, the applicant shall provide the City with a FM CE
black line clear Mylar(0.4 mil) copy and a blue fine print of the recorded
map.
35. Prior to the final inspection of any public improvements, the applicant FM CE
shall submit a written statement from a registered civil engineer that all
work has been completed and is in full compliance with the approved
plans.
36. Prior to the final inspection, the applicant shall submit a written BP,GP CE
certification from a registered civil engineer or land surveyor that all
survey monuments have been set as shown on the final map.
37. An encroachment permit shall be obtained prior to any work within City BP,GP CE
rights of way.
38. Prior to the issuance of building permits the applicant shall submit a BP,GP CE
grading and drainage plan prepared by a registered civil engineer for
review and approval by the City Engineer.
Atascadero Mutual Water Company
39. Before the issuance of building permits,the applicant shall submit plans
to AMWC for the water distribution facilities needed to serve the project.
AMWC shall review and approve the plans before construction begins
on the water system improvements. All water distribution facilities shall
be constructed in conformance with AMWC Standards and Details and
the California Waterworks Standards(Code of Regulations Title 22,
Division 4,Chapter 16). All cross-connection devices shall conform to
AWWA and California Department of Health Services standards.
40. Before the start of construction on the water system improvements,the
applicant shall pay all installation and connection fees required by
AMWC. Subject to the approval of AMWC,the applicant may enter in
to a"deferred connection"agreement,
41. Before issuance of building permits, the applicant shall obtain a"Will
Serve"letter from AMWC for the newly created lots within the
subdivision.
City of Atascadero
Resolution No.2005-077
Page 12 of 17
Conditions of Approval/ Timing Responsibility Mitigation
qtr Mitigation Monitoring Program /Monitoring Measure
GP:Grading Pernut PS.Planning Services
BP:Building Permit BS:Building Servbes
The Village at Oakhaven SIP:Subdivision FD:Fire Department
Improvement Plans PD:Police Department
Vesting Tentative Tract Map FM:Final Map CE:Crty Engineer
10:Temporary WW:Wastewater
TTM 2005-0067 occupancy CA:City Attorney
FI:Final inspection AMWC:Water Corp.
F0:Final Occupancy
42. The applicant shall provide AMWC with easements for those water
facilities proposed for operation and maintenance by AMWC that are
constructed outside of publicly maintained right-of-ways. AMWC shall
review the form and content of the easements before recordation.
43. The water mains required to serve the project shall be laid out in a grid
or looped pattern and shall connect to the existing water mains system
in EI Camino Beal at two points of connection.
44. The applicant shall provide AMWC with easements for those water
facilities proposed for operation and maintenance by AMWC that are
constructed outside of publicly maintained right-of-ways. AMWC shall
review the form and content of the easernents before recordation.
45. The applicant shall submit a hydraulic analysis to AW MC for the water
system improvements for the project. The analysis should take into
account the fire flows required by the Uniform Fire Code and
requirements of the California Waterworks Standards. The applicant is
responsible for designing and constructing water system improvements
that will provide water at pressures and flows adequate for the domestic
and fire protection needs of the project
46. The applicant is responsible for designing and constructing water
system improvements that will provide water at pressures and flows
adequate for the domestic and fire protection needs of the project.
47. The applicant shall obtain a separate landscape-irrigation meter from
AMWC for the common areas within the project.
48. Before construction of the water system improvements,AMWC shall
review and approve the landscape plans for the common areas within
the project.The landscape plan submittal shall incorporate the following
• Plant list w/ Water Use Classification of Landscape Species
(WUCOLS) rating specified. Preference shall be given to plants
with very low(VL) and low(L)WUCOLS ratings.
■ Justification for use of plants with WUCOLS rating of M or greater.
• Total landscaped area including hardscapes (patios, walks &
decks) and planted areas and excluding sidewalks, driveways,
streets or parking.
• The size and shape of turf areas shall promote for efficient
irrigation shall be no less than 8-feet wide. Turf type shall be
warm-season grasses. Turf areas shall be kept to a minimum and
shall be limited to functional areas only. A goal of the landscape
design should be a total turf area of no more than 10%of the total
landscaped area
49. Before construction of the water system improvements,AMWC shall
review and approve the irrigation plans for the common areas within the
ltlr+' project. The irrigation plan submittal shall include the following
. City of Atascadero
Resolution No.2005-077
Page 13 of 17
Conditions of Approval/ Timing Responsibility Mitigation
'err► Mitigation Monitoring Program /Monitoring Measure
GP:Grading Permit PS:Planning Services
BP:Building Perm! BS:Building Services
The Village at Oakhaven SIP:SubdNision FD:FireDeparlmenl
VestingIrriptovement Tentative Tract Ma FM:
PD:PoyEnginlice arlmenl
p FM:Final Map CE:City Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA:City Attorney
FI:Final inspection AMWC:Water Comp.
FO:Final Occupancy
• Landscape irrigation meter location and size.
■ Backflow prevention device type, location, and
manufacturer
• Flow and precipitation rate for each circuit
• Irrigation schedules including schedules for establishment
period and post establishment period
■ Total anticipated water application per circuit per month
for both schedules
• Total landscape water application.
• Use drip irrigation where ever possible
• A check valve shall be installed on the lowest head in
each sprinkler circuit
Mitigation Measures
Mitigation Measure 1.c.1:The project shall maintain a minimum 35-foot BP PS 1.c.1
setback from the eastern property line. A mi9nimum 10-foot wide landscape
buffer shall be installed by the developer prior to final and a deed restriction
shall be recorded against parcel 24,25, and 26 requiring continued
maintenance of the landscape buffer.The buffer area shall include
evergreen screen trees such as live oaks and/or cedars.
Mitigation Measure 1.d.1: All lighting shall be designed to eliminate any off BP PS�
site glare. All exterior site lights shall utilize full cut-off,"hooded"lighting
fixtures to prevent offsite light spillage and glare. Any luminaire pole height
shall not exceed 14-feet in height, limit intensity to 2.0 foot candles at
ingress/egress,and otherwise 0.6 foot candle minimum to 1.0 maximum in
parking areas. Fixtures shall be shield cut-off type.
Mitigation Measure 3.b.1: The project shall be conditioned to comply with all BP BS 3,b.1
applicable District regulations pertaining to the control of fugitive dust(PM-
10)as contained in sections 6.3, 6.4 and 6.5 of the April 2003 Air Quality
Handbook.
■ Asbestos has been identified by the state Air Resources Board as a
toxic air contaminant. Serpentine and ultramafic rocks are very
common in the state and may contain naturally occurring asbestos.
Under the State Air Resources Board Air Toxics Control Measure
(ATCM)for Construction, Grading, Quarrying, and Surface Mining
Operations,prior to any grading activities at the site,the project
proponent shall ensure that a geologic evaluation is conducted to
determine if naturally occurring asbestos is present within the area
that will be disturbed. If Naturally Occurring Asbestos (NOA) is found
at the site the applicant must comply with all requirements outlined in
the Asbestos ATCM for Construction, Grading,Quarrying,and
Surface Mining Operations. . If NOA is not present, an exemption
request must be filed with the District. If NOA is found at the site the
applicant must comply with all requirements outlined in the Asbestos
ATCM. This may include development of an Asbestos Dust
Mitigation Plan and an Asbestos Health and Safety Program for
111111110- approval by the APCD. Should Naturally Occurring Asbestos be
• City of Ataseadero
Resolution No.2005-077
Page 14 of 17
Conditions of Approval/ Timing Responsibility Mitigation
r Mitigation Monitoring Program /Monitoring Measure
GP Grading Permit PS:Planning Services
BP:Building Pernit BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:Fre Department
Improvement Plans PD:Police Department
Vesting Tentative Tract Map FM:Final Map CE:City Engineer
TTM 2005-0067 TO:Temporary WW:Wastewater
Occupancy CA City Attorney
FI:Final inspection AMWC:Water Comp.
F0:Final Occupancy
identified within the area of construction, and the worked area will be
less than or equal to one acre,then the dust control measures
identified below are required. If the disturbed area is greater than one
acre,additional requirements may include but are not limited to 1)an
Asbestos Dust Mitigation Plan which must be approved by the District
before construction begins, and 2)an Asbestos Health and Safety
Program will also be required for some projects.
■ Dust Control Measures for Construction and Grading Operation
Projects One Acre or Less: No person shall engage in any
construction or grading operation on property where the area to be
disturbed is one(1.0)acre or less unless all of the following dust
mitigation measures are initiated at the start and maintained
throughout the duration of the construction or grading activity:
(A)Construction vehicle speed at the work site must be limited to
fifteen(15) miles per hour or less;
(B) Prior to any ground disturbance,sufficient water must be
applied to the area to be disturbed to prevent visible emissions
fir►' from crossing the property line;
(C)Areas to be graded or excavated must be kept adequately
wetted to prevent visible emissions from crossing the property
line;
(D) Storage piles must be kept adequately wetted,treated with a
chemical dust suppressant,or covered when material is not
being added to or removed from the pile;
(E) Equipment must be washed down before moving from the
property onto a paved public road;and
(F)Visible track-out on the paved public road must be cleaned
using wet sweeping or a HEPA filter equipped vacuum device
within twenty-four 24 hours
City of Ataseadero
Resolution No.2005-077
Page 15 of 17
Conditions of Approval/ Timing Responsibility Mitigation
*AW Mitigation Monitoring Program /Monitoring Measure
GP:Grading Per" PS:Planning Services
BP:Building Permil BS:Building Services
The Village at Oakhaven SIP:subdivision FD:Fire Department
Improvement Plans PD:Police Department
Vesting Tentative Tract Map FM:Final Map CE:City Engineer
TTM 2005-0067
TO:pancyra y WW Wastewater
Occupancy Attorney
FI:Final inspection AMWC:Water Comp.
F0:Final Occupancy
Mitigation Measure 3.b.1: Naturally Occurring Asbestos(NOA) has been BP PS 3.b.1
identified by the state Air Resources Board as a toxic air contaminant.
Serpentine and ultramafic rocks are very common in the state and may
contain naturally occurring asbestos. Under the State Air Resources Board
Air Toxics Control Measure(ATCM)for Construction,Grading, Quarrying,
and Surface Mining Operations, prior to any grading activities at the site,the
project proponent shall ensure that a geologic evaluation is conducted to
determine if naturally occurring asbestos is present within the area that will
be disturbed. If naturally occurring asbestos is found at the site the
applicant must comply with all requirements outlined in the Asbestos ATCM
for Construction, Grading,Quarrying, and Surface Mining Operations.
These requirements may include but are not limited to 1) an Asbestos Dust
Mitigation Plan which must be approved by the District before construction
begins,and 2)an Asbestos Health and Safety Program will also be required
for some projects.
Mitigation Measure 4.e.1: The Grading Plan shall identify tree protection BP PS 4.e.1
fencing around the dripline,or as recommended by the project arborist,of
each existing on-site or off-site native tree.
Mitigation Measure 4.e.2: Grading and excavation and grading work shall GP PS 4.e.2
be consistent with the City of Atascadero Tree Ordinance. Special
precautions when working around native trees include:
1. All existing trees outside of the limits of work shall remain.
2. Earthwork shall not exceed the limits of the project area.
3. Low branches in danger of being torn from trees shall be pruned
prior to any heavy equipment work being done.
4. Vehicles and stockpiled material shall be stored outside the dripline
of all trees.
5. All trees within the area of work shall be fenced for protection with
4-foot chain link, snow or safety fencing placed per the approved
tree protection plan. Tree protection fencing shall be in place prior
to any site excavation or grading. Fencing shall remain in place
until completion of all construction activities.
6. Any roots that are encountered during excavation shall be clean cut
by hand and sealed with an approved tree seal.
City of Ataseadero
Resolution No.2005-077
Page 16 of 17
Conditions of Approval/ Timing Responsibility Mitigation
,+ Mitigation Monitoring Program /Monitoring Measure
GP Grading Permt PS:Planning Services
BP:Building Perrril BS:Building Services
The Village at Oakhaven SIP:subdivision FD:Fire Departmirl
Inprovernent Plans PD:Police Deparlmenl
Vesting Tentative Tract Map FM:Final Map CE:City Engineer
T0:Temporary WW:Wastewater
TTM 2005-0067 occupancy CA:City Attorney
FI:Final inspection AMWC:Water Corp.
F0:Final Occupancy
Mitigation Measure 4.e.3: The developer shall contract with a certified GP PS 4.e.3
arborist during all phases of project implementation. The certified arborists
shall be responsible for monitoring the project during all phases of
construction through project completion, as follows:
(a) A written agreement between the arborist and the developer outlining a
arborist monitoring schedule for each construction phase through final
inspection shall be submitted to and approved by planning staff prior to
the issuance of building/grading permits.
(b) Arborist shall schedule a pre-construction meeting with engineering
/planning staff,grading equipment operators, project superintendent to
review the project conditions and requirements prior to any grubbing or
earth work for any portion of the project site. All tree protection fencing
and trunk protection shall be installed for inspection during the meeting.
Tree protection fencing shall be installed at the line of encroachment
into the tree's root zone area.
(c) As specified by the arborist report and City staff:
• Prune all trees in active development areas to be saved for
structural strength and crown cleaning by a licensed and certified
arborist;
■ Remove all debris and spoils from the lot cleaning and tree pruning.
■ In locations where paving is to occur within the tree canopy, grub
only and do not grade nor compact. Install porous pavers over a
three-inch bed of 3/4 inch granite covered with one-inch pea gravel
for screeding. If curbs are required,use pegged curbs to secure the
porous pavers. Pegged curbs are reinforced six to eight curbs
poured at grade with a one-foot by one-foot pothole every four to six
linear feet.
■ All trenching or grading within the protected root zone area,outside
of the tree protection fence shall require hand trenching or preserve
and protect roots that are larger than 2 inches in diameter.
• No grading or trenching is allowed within the fenced protected area.
■ Any roots that are 4 inches in diameter or larger are not to be cut
until inspected and approved by the on-site arborist.
(d) Upon project completion and prior to final occupancy a final status
report shall be prepared by the project arborist certifying that the tree
protection plan was implemented, the trees designated for protection
were protected during construction, and the construction-related tree
protection measures are no longer required for tree protection.
Mitigation Measure 5.b.1: Should any cultural resources be unearthed GP,BP PS,BS
during site development work,the provisions of CEQA-Section 15064.5,will
be followed to reduce impacts to a non-significant level. —
tr►'
City of Ataseadero
Resolution No.2005-077
Page 17 of 17
Conditions of Approval/ Timing Responsibility Mitigation
r Mitigation Monitoring Program /Monitoring Measure
OF:Grading Permit PS:Planning Services
BP:Building Permit BS:Building Services
The Village at Oakhaven SIP:Subdivision FD:FireDepanrnent
Improvement Plans PD:Police Department
Vesting Tentative Tract Map FM:Final Map CE:City Engineer
TO:Temporary WW:Wastewater
TTM 2005-0067 Occupancy GN City Attorney
FI:Final inspection AMWC:Water Comp.
FO:Final Occupancy
Mitigation Measure 6.b: The grading permit application plans shall include GP CE 6.b
erosion control measures to prevent soil,dirt, and debris frorn entering the
storm drain system during and after construction. A separate plan shall be
submitted for this purpose and shall be subject to review and approval of the
City Engineer at the time of Building Permit application. (See section 8 of the
is document).
Mitigation Measure 6.c.d: A soils report shall be required to be submitted GP BS 6.c.d
with a future building permit by the building department.The building plans
will be required to follow the recommendations of the soils report to assure
safety for residents and buildings.
Mitigation Measure 8e.f.1: A Stormwater Pollution Prevention Plan BP CE 8.0
(SWPPP)/Erosion Control Plan shall be submitted and approved by the City
Engineer prior to the issuance of the building permit. The plan shall include
storm water measures for the operation and maintenance of the project for
the review and approval of the City Engineer. The Building Permit
application plans shall identify Best Management Practices (BMPs)
appropriate to the uses conducted on site that effectively prohibit the entry of
pollutants into storm water runoff.
Mitigation Measure 8.e.f.2: The developer is responsible for ensuring that BP BS,PS,CE 8.0.2
all contractors are aware of all storm water quality measures and that such
measures are implemented. Failure to comply with the approved
construction Best Management Practices will result in the issuance of
correction notices,citations, or stop work orders.
Mitigation Measure 11.d: All construction activities shall comply with the Ongoing BS/PS 11A
City of Atascadero Noise Ordinance for hours of operation.
Mitigation Measure 15.a.b.1: Full frontage improvernents shall be required BP BS,PS 15.a.b.1
along EI Camino Real. Internal project circulation shall be designed to
enhance flow and minimize traffic conflicts by implementing traffic calming
measures and utilizing one-way streets as appropriate and as approved by
the Community Development Director.
Mitigation Measure 15.c.1: The Contractor shall maintain one lane for traffic Ongoing BS,PS 15.0
at all times. Traffic control shall be in accordance with the current Caltrans
manual for traffic control and work area traffic control handbook. No street
or lane closures shall be permitted unless previously arranged for and
granted by the City Engineering Department.
err